WBS | Work Description |
Progress as on: 30-April-2022 |
Total Qty | Today Done (%) | Total Done (%) | Start | Finish |
01.2.2 |
Other-Excavation upto 2nd Bracing |
0 |
40 |
100 |
21-03-22 |
27-03-22 |
01.2.3 |
Other-Excavation upto Mat |
0 |
100 |
100 |
04-04-22 |
10-04-22 |
01.3.1.2 |
Bracing-1st Layer Installation |
488m2 |
30 |
100 |
16-03-22 |
20-03-22 |
01.3.2.1 |
Bracing-2nd Layer-Bracket Fixing |
52nos |
100 |
100 |
28-03-22 |
29-03-22 |
01.3.2.2 |
Bracing-2nd Layer Installation |
488m2 |
100 |
100 |
30-03-22 |
03-04-22 |
01.4.2 |
Pile Gap Filling upto 2nd Bracing |
154gap |
100 |
100 |
28-03-22 |
03-04-22 |
01.4.3 |
Pile Gap Filling upto Mat |
154gap |
100 |
100 |
11-04-22 |
17-04-22 |