Total Duration: |
230 |
days |
Total Working Days: |
83 |
Total Manpower: |
3831 |
|
|
Planning Progress = 100% |
Acual Progress = 98.6% |
SPI: 0.99 |
Behind Schedule |
Progress as on: 3-June-2022
WBS |
Work Description |
Total Quantity |
Total Done |
Schedule Start
| Schedule Finish |
Actual Start |
Actual Finish |
Lead-Lag(day) |
Not Yet |
1.1 |
Mobilization-Labour |
0 |
100% |
18-10-21 |
30-10-21 |
16-10-21 |
12-11-21 |
-13 |
|
1.2 |
Mobilization-Material |
0 |
100% |
18-10-21 |
31-10-21 |
16-10-21 |
02-11-21 |
-2 |
|
1.3.01 |
Mobilization-Shutter-Scaffolding |
50set |
100% |
18-10-21 |
02-11-21 |
20-10-21 |
13-11-21 |
-11 |
|
1.3.02 |
Mobilization-Shutter-Pipe,Clamp,BasePlat |
164m |
100% |
18-10-21 |
02-11-21 |
21-10-21 |
13-11-21 |
-11 |
|
1.3.03 |
Mobilization-Shutter-RetainingWall |
368m2 |
100% |
18-10-21 |
31-10-21 |
24-10-21 |
04-11-21 |
-4 |
|
1.3.04 |
Mobilization-Shutter-Column |
7set |
100% |
18-10-21 |
24-10-21 |
10-11-21 |
10-11-21 |
-17 |
|
1.3.05 |
Mobilization-Shutter-Shear Wall |
225m2 |
100% |
08-11-21 |
15-11-21 |
14-11-21 |
18-11-21 |
-3 |
|
1.3.06 |
Mobiliz-Shutter-Basement-1-South-Slab |
862m2 |
100% |
09-11-21 |
19-11-21 |
16-11-21 |
11-01-22 |
-53 |
|
1.3.07 |
Mobilize-Shutter-Basement-1-North-Slab |
862m2 |
100% |
23-11-21 |
03-12-21 |
29-12-21 |
12-01-22 |
-40 |
|
1.3.08 |
Mobiliz-Shutter-Ground Floor-South-Slab |
862m2 |
100% |
04-02-22 |
14-02-22 |
07-03-22 |
23-04-22 |
-68 |
|
1.3.09 |
Mobilize Shutter-Ramp |
1nos |
100% |
15-01-22 |
22-01-22 |
27-12-21 |
28-01-22 |
-6 |
|
1.3.10 |
Mobiliz-Shutter-RetainingWall-Basement-1 |
368m2 |
100% |
18-01-22 |
27-01-22 |
09-02-22 |
14-02-22 |
-18 |
|
2.1.1.1 |
Basement-2-South-RetainingWall-2nd-Re-ba |
147m2 |
100% |
10-11-21 |
14-11-21 |
21-10-21 |
18-11-21 |
-4 |
|
2.1.1.2 |
Basement-2-South-RetainingWall-2nd-Formw |
294m2 |
100% |
14-11-21 |
18-11-21 |
15-11-21 |
18-11-21 |
0 |
|
2.1.1.3 |
Basement-2-South-RetainingWall-2nd-Inspe |
147m2 |
100% |
19-11-21 |
19-11-21 |
18-11-21 |
18-11-21 |
1 |
|
2.1.1.4 |
Basement-2-South-RetainingWall-2nd-Concr |
147m2 |
100% |
20-11-21 |
20-11-21 |
18-11-21 |
18-11-21 |
2 |
|
2.1.2.1.1 |
Basement-2-South-Column-2nd-Re-bar |
6nos |
100% |
12-11-21 |
14-11-21 |
14-11-21 |
18-11-21 |
-4 |
|
2.1.2.1.2 |
Basement-2-South-Column-2nd-Formwork |
6nos |
100% |
14-11-21 |
16-11-21 |
14-11-21 |
18-11-21 |
-2 |
|
2.1.2.1.3 |
Basement-2-South-Column-2nd-Inspection |
6nos |
100% |
16-11-21 |
17-11-21 |
18-11-21 |
18-11-21 |
-1 |
|
2.1.2.1.4 |
Basement-2-South-Column-2nd-Concreting |
6nos |
100% |
17-11-21 |
17-11-21 |
18-11-21 |
18-11-21 |
-1 |
|
2.1.3.1 |
Basement-1-South-Slab-Formwork |
862m2 |
100% |
21-11-21 |
26-11-21 |
25-11-21 |
11-01-22 |
-46 |
|
2.1.3.2 |
Basement-1-South-Slab-Re-bar Work |
862m2 |
100% |
27-11-21 |
29-11-21 |
14-12-21 |
11-01-22 |
-43 |
|
2.1.3.3 |
Basement-1-South-Slab-Levelling |
862m2 |
100% |
30-11-21 |
30-11-21 |
11-01-22 |
12-01-22 |
-43 |
|
2.1.3.4 |
Basement-1-South-Slab-Inspection |
862m2 |
100% |
01-12-21 |
01-12-21 |
17-01-22 |
17-01-22 |
-47 |
|
2.1.3.5 |
Basement-1-South-Slab-Conreting |
862m2 |
100% |
02-12-21 |
02-12-21 |
17-01-22 |
17-01-22 |
-46 |
|
2.1.4.1 |
Basement-2-South-Stair-Form Work |
1no. |
100% |
23-11-21 |
28-11-21 |
19-12-21 |
11-01-22 |
-44 |
|
2.1.4.2 |
Basement-2-South-Stair-Rebar Work |
1no. |
100% |
28-11-21 |
01-12-21 |
19-12-21 |
11-01-22 |
-41 |
|
2.1.4.3 |
Basement-2-South-Stair-Inspection |
1no. |
100% |
01-12-21 |
01-12-21 |
17-01-22 |
17-01-22 |
-47 |
|
2.1.4.4 |
Basement-2-South-Stair-Concreting |
1no. |
100% |
02-12-21 |
02-12-21 |
17-01-22 |
17-01-22 |
-46 |
|
2.2.1.1.1 |
Basement-2-North-RetainingWall-1st-Re-ba |
92m2 |
100% |
29-10-21 |
31-10-21 |
24-10-21 |
05-11-21 |
-5 |
|
2.2.1.1.2 |
Basement-2-North-RetainingWall-1st-Formw |
184m2 |
100% |
31-10-21 |
04-11-21 |
30-10-21 |
05-11-21 |
-1 |
|
2.2.1.1.3 |
Basement-2-North-RetainingWall-1st-Inspe |
92m2 |
100% |
05-11-21 |
05-11-21 |
04-11-21 |
04-11-21 |
1 |
|
2.2.1.1.4 |
Basement-2-North-RetainingWall-1st-Concr |
92m2 |
100% |
06-11-21 |
06-11-21 |
05-11-21 |
05-11-21 |
1 |
|
2.2.1.2.1 |
Basement-2-North-RetainingWall-2nd-Re-ba |
147m2 |
100% |
07-11-21 |
07-11-21 |
10-11-21 |
12-11-21 |
-5 |
|
2.2.1.2.2 |
Basement-2-North-RetainingWall-2nd-Formw |
294m2 |
100% |
08-11-21 |
10-11-21 |
10-11-21 |
12-11-21 |
-2 |
|
2.2.1.2.3 |
Basement-2-North-RetainingWall-2nd-Inspe |
147m2 |
100% |
11-11-21 |
11-11-21 |
12-11-21 |
12-11-21 |
-1 |
|
2.2.1.2.4 |
Basement-2-North-RetainingWall-2nd-Concr |
147m2 |
100% |
12-11-21 |
12-11-21 |
12-11-21 |
12-11-21 |
0 |
|
2.2.2.1.1 |
Basement-2-Shear Wall-1st-ReBarWork |
90m2 |
100% |
15-11-21 |
17-11-21 |
20-11-21 |
26-11-21 |
-9 |
|
2.2.2.1.2 |
Basement-2-Shear Wall-1st-Formwork |
180m2 |
100% |
17-11-21 |
22-11-21 |
21-11-21 |
26-11-21 |
-4 |
|
2.2.2.1.3 |
Basement-2-Shear Wall-1st-Inspection |
90m2 |
100% |
22-11-21 |
23-11-21 |
26-11-21 |
26-11-21 |
-3 |
|
2.2.2.1.4 |
Basement-2-Shear Wall-1st-Concreting |
90m2 |
100% |
23-11-21 |
24-11-21 |
26-11-21 |
26-11-21 |
-2 |
|
2.2.2.2.1 |
Basement-2-Shear Wall-2nd-ReBarWork |
90m2 |
100% |
25-11-21 |
27-11-21 |
30-11-21 |
10-12-21 |
-13 |
|
2.2.2.2.2 |
Basement-2-Shear Wall-2nd-Formwork |
180m2 |
100% |
27-11-21 |
02-12-21 |
05-12-21 |
10-12-21 |
-8 |
|
2.2.2.2.3 |
Basement-2-Shear Wall-2nd-Inspection |
90m2 |
100% |
02-12-21 |
03-12-21 |
10-12-21 |
10-12-21 |
-7 |
|
2.2.2.2.4 |
Basement-2-Shear Wall-2nd-Concreting |
90m2 |
100% |
03-12-21 |
04-12-21 |
10-12-21 |
10-12-21 |
-6 |
|
2.2.3.1.1 |
Basement-2-Water Reservoir-1st-RebarWork |
109m2 |
100% |
20-11-21 |
22-11-21 |
20-11-21 |
26-11-21 |
-4 |
|
2.2.3.1.2 |
Basement-2-Water Reservoir-1st-Formwork |
217m2 |
100% |
22-11-21 |
24-11-21 |
22-11-21 |
26-11-21 |
-2 |
|
2.2.3.1.3 |
Basement-2-Water Reservoir-1st-Inspectio |
109m2 |
100% |
25-11-21 |
25-11-21 |
26-11-21 |
26-11-21 |
-1 |
|
2.2.3.1.4 |
Basement-2-Water Reservoir-1st-Concretin |
109m2 |
100% |
26-11-21 |
26-11-21 |
26-11-21 |
26-11-21 |
0 |
|
2.2.3.2.1 |
Basement-2-Water Reservoir-2nd-ReBarWork |
109m2 |
100% |
21-01-22 |
21-01-22 |
30-11-21 |
28-01-22 |
-7 |
|
2.2.3.2.2 |
Basement-2-Water Reservoir-2nd-Formwork |
217m2 |
100% |
22-01-22 |
26-01-22 |
01-12-21 |
28-01-22 |
-2 |
|
2.2.3.2.3 |
Basement-2-Water Reservoir-2nd-Inspectio |
109m2 |
100% |
26-01-22 |
26-01-22 |
10-12-21 |
30-01-22 |
-4 |
|
2.2.3.2.4 |
Basement-2-Water Reservoir-2nd-Concretin |
109m2 |
100% |
26-01-22 |
26-01-22 |
10-12-21 |
30-01-22 |
-4 |
|
2.2.4.1.1 |
Basement-2-North-Column-1st-ReBarWork |
1no |
100% |
21-11-21 |
23-11-21 |
24-11-21 |
24-11-21 |
-1 |
|
2.2.4.1.2 |
Basement-2-North-Column-1st-Formwork |
1no |
100% |
23-11-21 |
25-11-21 |
25-11-21 |
25-11-21 |
0 |
|
2.2.4.1.3 |
Basement-2-North-Column-1st-Inspection |
1no |
100% |
25-11-21 |
26-11-21 |
26-11-21 |
25-11-21 |
1 |
|
2.2.4.1.4 |
Basement-2-North-Column-1st-Conctreting |
1no |
100% |
26-11-21 |
27-11-21 |
26-11-21 |
26-11-21 |
1 |
|
2.2.4.2.1 |
Basement-2-North-Column-2nd-ReBarWork |
1no |
100% |
28-11-21 |
30-11-21 |
05-12-21 |
10-12-21 |
-10 |
|
2.2.4.2.2 |
Basement-2-North-Column-2nd-Formwork |
1no. |
100% |
30-11-21 |
02-12-21 |
05-12-21 |
10-12-21 |
-8 |
|
2.2.4.2.3 |
Basement-2-North-Column-2nd-Inspection |
1no. |
100% |
02-12-21 |
03-12-21 |
10-12-21 |
10-12-21 |
-7 |
|
2.2.4.2.4 |
Basement-2-North-Column-2nd-Conctreting |
1no. |
100% |
03-12-21 |
04-12-21 |
10-12-21 |
10-12-21 |
-6 |
|
2.2.5.1 |
Basement-1-North-Slab-Formwork |
862m2 |
100% |
05-12-21 |
09-12-21 |
27-12-21 |
11-01-22 |
-33 |
|
2.2.5.2 |
Basement-1-North-Slab-Re-bar Work |
862m2 |
100% |
10-12-21 |
11-12-21 |
31-12-21 |
11-01-22 |
-31 |
|
2.2.5.3 |
Basement-1-North-Slab-Levelling |
862m2 |
100% |
12-12-21 |
12-12-21 |
11-01-22 |
12-01-22 |
-31 |
|
2.2.5.4 |
Basement-1-North-Slab-Inspection |
862m2 |
100% |
13-12-21 |
13-12-21 |
17-01-22 |
17-01-22 |
-35 |
|
2.2.5.5 |
Basement-1-North-Slab-Concreting |
862m2 |
100% |
14-12-21 |
14-12-21 |
17-01-22 |
17-01-22 |
-34 |
|
2.2.6.1 |
Basement-2-North-Stair-Formwork |
1no. |
100% |
05-12-21 |
10-12-21 |
27-12-21 |
11-01-22 |
-32 |
|
2.2.6.2 |
Basement-2-North-Stair-Rebar work |
1no. |
100% |
10-12-21 |
13-12-21 |
27-12-21 |
11-01-22 |
-29 |
|
2.2.6.3 |
Basement-2-North-Stair-Inspection |
1no. |
100% |
13-12-21 |
14-12-21 |
17-01-22 |
17-01-22 |
-34 |
|
2.2.6.4 |
Basement-2-North-Stair-Concreting |
1no. |
100% |
14-12-21 |
14-12-21 |
17-01-22 |
17-01-22 |
-34 |
|
2.2.7.1 |
Basement-2-Ramp-Formwork |
1no. |
100% |
22-01-22 |
25-01-22 |
27-12-21 |
30-01-22 |
-5 |
|
2.2.7.2 |
Basement-2-Ramp-Rebar-work |
1no. |
100% |
25-01-22 |
26-01-22 |
27-12-21 |
30-01-22 |
-4 |
|
2.2.7.3 |
Basement-2-Ramp-Inspection |
1no. |
100% |
26-01-22 |
26-01-22 |
30-01-22 |
30-01-22 |
-4 |
|
2.2.7.4 |
Basement-2-Ramp-Concreting |
1no. |
100% |
26-01-22 |
26-01-22 |
30-01-22 |
30-01-22 |
-4 |
|
3.1.1.1.1 |
Basement-1-South-RetainingWall-1st-ReBar |
176m2 |
100% |
26-01-22 |
28-01-22 |
20-01-22 |
24-01-22 |
4 |
|
3.1.1.1.2 |
Basement-1-South-RetainingWall-1st-Formw |
352m2 |
100% |
28-01-22 |
01-02-22 |
09-02-22 |
14-02-22 |
-13 |
|
3.1.1.1.3 |
Basement-1-South-RetainingWall-1st-Inspe |
176m2 |
100% |
02-02-22 |
02-02-22 |
14-02-22 |
14-02-22 |
-12 |
|
3.1.1.1.4 |
Basement-1-South-RetainingWall-1st-Concr |
176m2 |
100% |
03-02-22 |
03-02-22 |
14-02-22 |
14-02-22 |
-11 |
|
3.1.1.2.1 |
Basement-1-South-RetainingWall-2nd-ReBar |
176m2 |
100% |
05-02-22 |
06-02-22 |
16-02-22 |
18-02-22 |
-12 |
|
3.1.1.2.2 |
Basement-1-South-RetainingWall-2nd-Formw |
352m2 |
100% |
07-02-22 |
11-02-22 |
18-02-22 |
26-02-22 |
-15 |
|
3.1.1.2.3 |
Basement-1-South-RetainingWall-2nd-Inspe |
176m2 |
100% |
12-02-22 |
12-02-22 |
26-02-22 |
26-02-22 |
-14 |
|
3.1.1.2.4 |
Basement-1-South-RetainingWall-2nd-Concr |
176m2 |
100% |
13-02-22 |
13-02-22 |
26-02-22 |
26-02-22 |
-13 |
|
3.1.2.1.1 |
Basement-1-South-Column-1st-Re-Bar Work |
6nos |
100% |
26-01-22 |
27-01-22 |
24-01-22 |
24-01-22 |
3 |
|
3.1.2.1.2 |
Basement-1-South-Column-1st-Formwork |
6nos |
100% |
28-01-22 |
29-01-22 |
14-02-22 |
18-02-22 |
-20 |
|
3.1.2.1.3 |
Basement-1-South-Column-1st-Inspection |
6m2 |
100% |
30-01-22 |
30-01-22 |
14-02-22 |
18-02-22 |
-19 |
|
3.1.2.1.4 |
Basement-1-South-Column-1st-Conreting |
6nos |
100% |
31-01-22 |
31-01-22 |
14-02-22 |
26-02-22 |
-26 |
|
3.1.2.2.1 |
Basement-1-South-Column-2nd-ReBarWork |
6nos |
100% |
01-02-22 |
02-02-22 |
20-02-22 |
26-02-22 |
-24 |
|
3.1.2.2.2 |
Basement-1-South-Column-2nd-Formwork |
6nos |
100% |
03-02-22 |
04-02-22 |
20-02-22 |
04-03-22 |
-28 |
|
3.1.2.2.3 |
Basement-1-South-Column-2nd-Inspection |
6nos |
100% |
05-02-22 |
05-02-22 |
26-02-22 |
13-03-22 |
-36 |
|
3.1.2.2.4 |
Basement-1-South-Column-2nd-Concreting |
6nos |
100% |
06-02-22 |
06-02-22 |
26-02-22 |
13-03-22 |
-35 |
|
3.1.3.1 |
Ground Floor Slab-South-Formwork |
862m2 |
100% |
16-02-22 |
22-02-22 |
04-03-22 |
23-04-22 |
-60 |
|
3.1.3.2 |
Ground Floor Slab-South-Re-bar Work |
862m2 |
100% |
23-02-22 |
01-03-22 |
31-03-22 |
23-04-22 |
-53 |
|
3.1.3.3 |
Ground Floor Slab-South-Levelling |
862m2 |
100% |
02-03-22 |
02-03-22 |
23-04-22 |
23-04-22 |
-52 |
|
3.1.3.4 |
Ground Floor Slab-South-Inspection |
862m2 |
100% |
03-03-22 |
03-03-22 |
23-04-22 |
23-04-22 |
-51 |
|
3.1.3.5 |
Ground Floor Slab-South-Concreting |
862m2 |
100% |
04-03-22 |
04-03-22 |
24-04-22 |
24-04-22 |
-51 |
|
3.1.4.1 |
Basement-1-South-Stair-Form Work |
1no. |
60% |
23-02-22 |
28-02-22 |
03-02-22 |
12-02-22 |
|
Completed |
3.1.4.2 |
Basement-1-South-Stair-Re-bar Work |
1no. |
60% |
28-02-22 |
03-03-22 |
18-02-22 |
26-02-22 |
|
Completed |
3.1.4.3 |
Basement-1-South-Stair-Inspection |
1no. |
50% |
03-03-22 |
04-03-22 |
31-03-22 |
31-03-22 |
|
Completed |
3.1.4.4 |
Basement-1-South-Stair-Concreting |
1no. |
50% |
04-03-22 |
04-03-22 |
31-03-22 |
31-03-22 |
|
Completed |
3.2.1.1.1 |
Basement-1-North-RetainingWall-1st-ReBar |
176m2 |
100% |
13-02-22 |
14-02-22 |
26-01-22 |
04-03-22 |
-18 |
|
3.2.1.1.2 |
Basement-1-North-RetainingWall-1st-Formw |
352m2 |
100% |
14-02-22 |
18-02-22 |
07-03-22 |
13-03-22 |
-23 |
|
3.2.1.1.3 |
Basement-1-North-RetainingWall-1st-Inspe |
176m2 |
100% |
19-02-22 |
19-02-22 |
13-03-22 |
13-03-22 |
-22 |
|
3.2.1.1.4 |
Basement-1-North-RetainingWall-1st-Concr |
176m2 |
100% |
20-02-22 |
20-02-22 |
13-03-22 |
13-03-22 |
-21 |
|
3.2.1.2.1 |
Basement-1-North-RetainingWall-2nd-ReBar |
176m2 |
100% |
23-02-22 |
24-02-22 |
22-03-22 |
27-03-22 |
-31 |
|
3.2.1.2.2 |
Basement-1-North-RetainingWall-2nd-Formw |
352m2 |
100% |
25-02-22 |
01-03-22 |
22-03-22 |
27-03-22 |
-26 |
|
3.2.1.2.3 |
Basement-1-North-RetainingWall-2nd-Inspe |
176m2 |
100% |
02-03-22 |
02-03-22 |
22-03-22 |
27-03-22 |
-25 |
|
3.2.1.2.4 |
Basement-1-North-RetainingWall-2nd-Concr |
176m2 |
100% |
03-03-22 |
03-03-22 |
22-03-22 |
27-03-22 |
-24 |
|
3.2.2.1.1 |
Basement-1-Shear Wall-1st-ReBarWork |
108m2 |
100% |
13-02-22 |
14-02-22 |
24-01-22 |
07-03-22 |
-21 |
|
3.2.2.1.2 |
Basement-1-Shear Wall-1st-Formwork |
216m2 |
100% |
14-02-22 |
18-02-22 |
04-03-22 |
13-03-22 |
-23 |
|
3.2.2.1.3 |
Basement-1-Shear Wall-1st-Inspection |
108m2 |
100% |
19-02-22 |
19-02-22 |
13-03-22 |
13-03-22 |
-22 |
|
3.2.2.1.4 |
Basement-1-Shear Wall-1st-Concreting |
108m2 |
100% |
20-02-22 |
20-02-22 |
23-03-22 |
27-03-22 |
-35 |
|
3.2.2.2.1 |
Basement-1-Shear Wall-2nd-Re-Bar Wprk |
108m2 |
100% |
22-02-22 |
23-02-22 |
23-03-22 |
27-03-22 |
-32 |
|
3.2.2.2.2 |
Basement-1-Shear Wall-2nd-Formwork |
216m2 |
100% |
24-02-22 |
28-02-22 |
27-03-22 |
27-03-22 |
-27 |
|
3.2.2.2.3 |
Basement-1-Shear Wall-2nd-Inspection |
108m2 |
100% |
01-03-22 |
01-03-22 |
27-03-22 |
27-03-22 |
-26 |
|
3.2.2.2.4 |
Basement-1-Shear Wall-2nd-Concreting |
108m2 |
100% |
02-03-22 |
02-03-22 |
23-03-22 |
27-03-22 |
-25 |
|
3.2.3.1.1 |
Basement-1-North-Column-1st-Re-bar Work |
1no. |
100% |
10-02-22 |
11-02-22 |
03-02-22 |
03-02-22 |
8 |
|
3.2.3.1.2 |
Basement-1-North-Column-1st-Formwork |
1no. |
100% |
12-02-22 |
14-02-22 |
13-03-22 |
13-03-22 |
-27 |
|
3.2.3.1.3 |
Basement-1-North-Column-1st-Inspection |
1no. |
100% |
15-02-22 |
15-02-22 |
13-03-22 |
13-03-22 |
-26 |
|
3.2.3.1.4 |
Basement-1-North-Column-1st-Concreting |
1no. |
100% |
16-02-22 |
16-02-22 |
13-03-22 |
13-03-22 |
-25 |
|
3.2.3.2.1 |
Basement-1-North-Column-2nd-Re-bar Work |
1no. |
100% |
18-02-22 |
19-02-22 |
31-03-22 |
23-04-22 |
-63 |
|
3.2.3.2.2 |
Basement-1-North-Column-2nd-Formwork |
1no. |
100% |
20-02-22 |
22-02-22 |
31-03-22 |
23-04-22 |
-60 |
|
3.2.3.2.3 |
Basement-1-North-Column-2nd-Inspection |
1no. |
100% |
23-02-22 |
23-02-22 |
31-03-22 |
23-04-22 |
-59 |
|
3.2.3.2.4 |
Basement-1-North-Column-2nd-Concreting |
1no. |
100% |
24-02-22 |
24-02-22 |
31-03-22 |
24-04-22 |
-59 |
|
3.2.4.1 |
Ground Floor Slab-North-Formwork |
862m2 |
100% |
05-03-22 |
09-03-22 |
31-03-22 |
23-04-22 |
-45 |
|
3.2.4.2 |
Ground Floor Slab-North-Re-bar Work |
862m2 |
100% |
10-03-22 |
12-03-22 |
23-04-22 |
23-04-22 |
-42 |
|
3.2.4.3 |
Ground Floor Slab-North-Levelling |
862m2 |
100% |
13-03-22 |
13-03-22 |
23-04-22 |
23-04-22 |
-41 |
|
3.2.4.4 |
Ground Floor Slab-North-Inspection |
862m2 |
100% |
14-03-22 |
14-03-22 |
23-04-22 |
23-04-22 |
-40 |
|
3.2.4.5 |
Ground Floor Slab-North-Concreting |
862m2 |
100% |
15-03-22 |
15-03-22 |
24-04-22 |
24-04-22 |
-40 |
|
3.2.5.1 |
Basement-1-North-Stair-Form Work |
1no. |
100% |
06-03-22 |
11-03-22 |
23-03-22 |
23-04-22 |
-43 |
|
3.2.5.2 |
Basement-1-North-Stair-Re-bar Work |
1no. |
100% |
11-03-22 |
14-03-22 |
27-03-22 |
23-04-22 |
-40 |
|
3.2.5.3 |
Basement-1-North-Stair-Inspection |
1no. |
100% |
14-03-22 |
15-03-22 |
31-03-22 |
23-04-22 |
-39 |
|
3.2.5.4 |
Basement-1-North-Stair-Concreting |
1no. |
100% |
15-03-22 |
15-03-22 |
31-03-22 |
24-04-22 |
-40 |
|
3.2.6.1 |
Basement-1-Ramp-Form Work |
1no. |
100% |
11-03-22 |
14-03-22 |
22-03-22 |
03-06-22 |
-81 |
|
3.2.6.2 |
Basement-1-Ramp-Re-bar Work |
1no. |
100% |
14-03-22 |
15-03-22 |
22-03-22 |
03-06-22 |
-80 |
|
3.2.6.3 |
Basement-1-Ramp-Inspection |
1no. |
100% |
15-03-22 |
15-03-22 |
23-04-22 |
03-06-22 |
-80 |
|
3.2.6.4 |
Basement-1-Ramp-Concreting |
1no. |
100% |
15-03-22 |
15-03-22 |
24-04-22 |
03-06-22 |
-80 |
|
Site Photographs |
|
Worker at evening on 16-10-21 |
|
Hardware materials mobilization on 16-10-21 |
|
|
|
Materials mobilization (Received) on 17-10-21 |
|
Labour picture 1st hour (morning) on 17-10-21 |
|
|
|
Mobilization work labour shed wiring on 18-10-21 |
|
Tool box meeting on 18-10-21 |
|
|
|
Tool Box meeting on 19-10-21 |
|
Service cable line work on 19-10-21 |
|
|
|
Toolbox meeting on 20-10-21 |
|
Column ring rod binding on 20-10-21 |
|
|
|
Toolbox meeting on 21-10-21 |
|
Rebar work on 21-10-21 |
|
|
|
Toolbox meeting on 22-10-21 |
|
Rebar work on 22-10-21 |
|
|
|
Toolbox Meeting on 23-10-21 |
|
Scaffolding Materials received at site on 23-10-21 |
|
|
|
North Retaining wall Rebar work on 24-10-21 |
|
Toolbox Meeting on 24-10-21 |
|
|
|
Toolbox meeting on 26-10-21 |
|
Retaining wall rebar binding on 26-10-21 |
|
|
|
Toolbox Metting on 27-10-21 |
|
Retaining wall shutter unloading on 27-10-21 |
|
|
|
Shutter Fixing on 30-10-21 |
|
Night Shift Work:Shutter hole making on 30-10-21 |
|
|
|
Shutter arrive at site on 31-10-21 |
|
Shuttering work on 31-10-21 |
|
|
|
Toolbox Meeting on 2-11-21 |
|
Materials mobilization on 2-11-21 |
|
|
|
North Retaining wall inspection on 4-11-21 |
|
Shutter mobilization on 4-11-21 |
|
|
|
Casting start on 5-11-21 |
|
Casting Finish on 5-11-21 |
|
|
|
Retaining Wall-North-2nd Lift-Re-bar Wor on 10-11-21 |
|
Retaining Wall-North-2nd Lift-Form Work on 10-11-21 |
|
|
|
Casting start picture on 12-11-21 |
|
Casting finishing picture on 12-11-21 |
|
|
|
Scaffolding Bumper on 13-11-21 |
|
Site picture on 13-11-21 |
Whole-day Rain on dated 13-11-2021 |
|
|
Site picture on 14-11-21 |
|
Shear wall shutter on 14-11-21 |
Whole-day Rain |
|
|
Shuttering work on 15-11-21 |
|
Shuttering at night on 15-11-21 |
|
|
|
South Retaining on 16-11-21 |
|
Mobilization slab materials on 16-11-21 |
|
|
|
South retaining wall on 17-11-21 |
|
Retaing wall work progress on 17-11-21 |
U-Head arrive at site |
|
|
Ready mix concreting with pump on 18-11-21 |
|
Concreting finish on 18-11-21 |
Concreting finish at 12:45PM on 19-11-2021 |
|
|
Site picture on 20-11-21 |
|
Shear wall shutter carrying to basement on 20-11-21 |
|
|
|
Shear wall shuttering on 21-11-21 |
|
Night work on 21-11-21 |
|
|
|
Water tank shuttering on 22-11-21 |
|
Beam Bottom shutter arrive at site parti on 22-11-21 |
|
|
|
Shear wall and water reservior shutterin on 24-11-21 |
|
Shuttering work on 24-11-21 |
|
|
|
South slab beam bottom shutter on 25-11-21 |
|
Inspection team on 25-11-21 |
|
|
|
Ready mix concreting on 26-11-21 |
|
Concreting work on 26-11-21 |
|
|
|
B1 Slab beam bottom shutter on 28-11-21 |
|
Slab south shutter mobilization on 28-11-21 |
|
|
|
South B1 Slab shuttering on 30-11-21 |
|
Slab shuttering on 30-11-21 |
|
|
|
Materials Mobilization on 1-12-21 |
|
Surface repairing on 1-12-21 |
|
|
|
Site picture on 5-12-21 |
|
Site picture on 5-12-21 |
Whole day rain |
|
|
Prepared for water discharge on 6-12-21 |
|
Rain time picture on 6-12-21 |
Whole day rain so no work |
|
|
Site picture on 8-12-21 |
|
Site picture on 8-12-21 |
|
|
|
Basement-1-North Side Slab Shuttering on 10-12-21 |
|
Concreting on 10-12-21 |
Water Resrvoir, Shear Wall, North Column -2nd Lift |
|
|
Slab shuttering work on 11-12-21 |
|
Site picture on 11-12-21 |
Only slab shuttering work today |
|
|
B1 south slab shuttering on 13-12-21 |
|
B1 south slab shuttering on 13-12-21 |
|
|
|
Plain sheet for slab on 14-12-21 |
|
Beam rebar binding of south slab on 14-12-21 |
|
|
|
South slab shuttering and rod binding on 15-12-21 |
|
Night work on 15-12-21 |
Today whole night duty |
|
|
South stair on 19-12-21 |
|
South slab form work and shuttering on 19-12-21 |
|
|
|
South slab work on 21-12-21 |
|
South slab rebar work on 21-12-21 |
Work stop on 21-12-2021 After lunch and again start at 10:30 pm to 11:45 PM but after again stop Due to PD |
|
|
North slab shuttering on 27-12-21 |
|
Site picture on 27-12-21 |
|
|
|
North slab shuttering on 29-12-21 |
|
North slab work on 29-12-21 |
|
|
|
North slab rebar work on 31-12-21 |
|
North slab shuttering work on 31-12-21 |
|
|
|
Basement-1-North Slab Re-bar Work on 2-01-22 |
|
Basement-1-North Slab Shuttering on 2-01-22 |
|
|
|
North slab work on 4-01-22 |
|
North slab work on 4-01-22 |
|
|
|
Basement-1-North slab work on 5-01-22 |
|
Basement-1-Slab shuttering on 5-01-22 |
Work stopped at 4:00 PM by PD |
|
|
Shuttering and rod binding on 9-01-22 |
|
Shuttering work on 9-01-22 |
|
|
|
North south slab work on 11-01-22 |
|
North south slab on 11-01-22 |
|
|
|
Slab levelling on 12-01-22 |
|
Slab levelling work on 12-01-22 |
|
|
|
Inspection by American & Local Consultan on 17-01-22 |
|
Basement-1-Slab Concreting on 17-01-22 |
Concreteing start 17.01.2022 8:45 PM and end 18.01.2022 10:30 AM |
|
|
Ramp shuttering work on 20-01-22 |
|
Retaining wall rrbar work on 20-01-22 |
|
|
|
Rebar work on 24-01-22 |
|
Ramp shuttering on 24-01-22 |
|
|
|
Ramp formwork going on on 26-01-22 |
|
Ramp formwork going on on 26-01-22 |
Work stopped afternoon due to rain |
|
|
Night work at ramp on 28-01-22 |
|
Ramp work on 28-01-22 |
|
|
|
Ramp work on 30-01-22 |
|
Ramp concreting on 30-01-22 |
|
|
|
Ramp concreted on 31-01-22 |
|
Ramp Curing work on 31-01-22 |
|
|
|
South stair shutter on 3-02-22 |
|
Overall site on 3-02-22 |
|
|
|
South Retaining wall on 9-02-22 |
|
South Retaining wall shuttering on 9-02-22 |
|
|
|
Basement-1-South Retaining wall on 12-02-22 |
|
Basement-1-South Retaining Wall-Shutteri on 12-02-22 |
|
|
|
Ready mix on 14-02-22 |
|
Concreting on 14-02-22 |
|
|
|
Basement-1-South retaining wall 2nd lift on 16-02-22 |
|
Basement-1-south retaining wall-Re-bar on 16-02-22 |
|
|
|
South 2nd lift retaining wall on 18-02-22 |
|
Shuttering work on 18-02-22 |
|
|
|
Retaining wall shuttering on 20-02-22 |
|
Column shuttering on 20-02-22 |
2nd Half was rain |
|
|
South retaining wall on 22-02-22 |
|
South stair work on 22-02-22 |
|
|
|
Basement-1-South retaining wall on 23-02-22 |
|
Basement-1-South Column shuttering on 23-02-22 |
|
|
|
Ready-mix Concrete Truck and Pump on 26-02-22 |
|
B-1-South 2nd Retaining wall concreting on 26-02-22 |
|
|
|
B-1-North retaining wall rebar work on 28-02-22 |
|
Basement-1-North Retaining wall-1st Lift on 28-02-22 |
|
|
|
GF slab beam bottom on 4-03-22 |
|
North Retaining wall on 4-03-22 |
|
|
|
North retaining wall on 7-03-22 |
|
South GF slab shutter on 7-03-22 |
|
|
|
Ready mix on 13-03-22 |
|
Ready mix concreting on 13-03-22 |
|
|
|
Ready mix on 22-03-22 |
|
Ready mix casting on 22-03-22 |
|
|
|
Slab shuttering on 23-03-22 |
|
Shear wall shuttering on 23-03-22 |
|
|
|
Ready mix casting on 27-03-22 |
|
North retaining wall 2nd complete on 27-03-22 |
|
|
|
Gr.Floor Slab shuttering and rod binding on 31-03-22 |
|
Ground Floor Beam Rebar binding on 31-03-22 |
|
|
|
GF slab work progress on 3-04-22 |
|
Work progress on 3-04-22 |
|
|
|
Inspaction on 23-04-22 |
|
Slab inspaction on 23-04-22 |
|
|
|
Ready mix Concrete Truck on 24-04-22 |
|
Ground Floor Slab concreting on 24-04-22 |
|
|
|
Site Shutter Remove on 9-05-22 |
|
Bracing Remove on 9-05-22 |
|
|
|
Ramp work on 26-05-22 |
|
Shutter opening on 26-05-22 |
|
|
|
Ready mix car on 3-06-22 |
|
Ready mix concreting on 3-06-22 |
|
|