DAILY PROGRES REPORT |
Project: | Urban Resilience Unit Building | Project Code: | 18 | Date | 3-June-2022 | ||
Client: | Rajuk | Report | 083 | Day | Friday | ||
Contractor: | Elevate Builders Ltd, | Climate | Sunny | ||||
Temperature | 28-33°C |
Manpower | ||
SN | Description | Nos |
---|---|---|
01 | Elivate-Staff | 7 |
02 | Civil Labor-Day Shift | 18 |
03 | Civil Labor-Night Shift | 10 |
TOTAL | 35 |
WBS | Work Description | Progress as on: 3-June-2022 | |||||
Total Qty | Today Done (%) | Total Done (%) | Start | Finish | |||
3.2.6.1 | Basement-1-Ramp-Form Work | 1no. | 10 | 100 | 11-03-22 | 14-03-22 | |
3.2.6.2 | Basement-1-Ramp-Re-bar Work | 1no. | 30 | 100 | 14-03-22 | 15-03-22 | |
3.2.6.3 | Basement-1-Ramp-Inspection | 1no. | 50 | 100 | 15-03-22 | 15-03-22 | |
3.2.6.4 | Basement-1-Ramp-Concreting | 1no. | 50 | 100 | 15-03-22 | 15-03-22 |