TOTAL PROGRES REPORT

From 18-September-2020 to 21-February-2022
Project Code: 58 Name: The View Hotel Kuakata
Client: Sikder Group Contractor:
Progress as on: 21-February-2022
Total Duration: 521 days Total Working Days: 73 Total Manpower: 6905
Planning Progress = 92.7% Acual Progress = 87.1% SPI: 0.94 Behind Schedule
WBS Work Description
Total Quantity Total Done Schedule Start Schedule Finish Actual Start Actual Finish Lead-Lag(day) Not Yet
1.1.01 Take-over Site for Construction 100% 18-09-20 18-09-20 18-09-20 18-09-20 0
2.1.01 Tower-1-Pile Work 301nos 100% 19-09-20 07-11-20 05-11-20 06-11-20 1
2.1.02 Tower-1-Pile Cap 26nos 100% 22-10-20 18-12-20 05-11-20 18-12-20 0
2.1.03 Tower-1-Padestal 31nos 100% 07-11-20 23-12-20 28-11-20 21-12-20 2
2.1.04 Tower-1-Lift Core Below GB 2nos 100% 12-12-20 23-12-20 09-12-20 21-12-20 2
2.1.05 Tower-1-Grade Beam 421rm 100% 09-12-20 30-12-20 30-11-20 27-01-21 -28
2.2.01.1 Tower-1-GF Column 31nos 100% 24-12-20 04-01-21 09-12-20 27-01-21 -23
2.2.01.2 Tower-1-GF-Lift Core 2nos 100% 24-12-20 04-01-21 21-12-20 27-01-21 -23
2.2.01.3 Tower-1-GF-Stair 2nos 100% 24-12-20 15-01-21 21-12-20 27-01-21 -12
2.2.01.4 Tower-1-1st Floor Slab 1505m2 100% 10-01-21 20-01-21 15-12-20 0
2.2.02.1 Tower-1-1st Floor Column 31nos 100% 22-01-21 31-01-21 27-12-20 07-02-21 -7
2.2.02.2 Tower-1-1st Floor Lift Core 2nos 100% 02-02-21 07-02-21 05-02-21 07-02-21 0
2.2.02.3 Tower-1-1st Floor Stair 2nos 100% 22-01-21 18-02-21 05-02-21 10-02-21 8
2.2.02.4 Tower-1-2nd Floor Slab 1672m2 100% 08-02-21 18-02-21 08-01-21 0
2.2.03.1 Tower-1-2nd Floor Column 31nos 100% 19-02-21 01-03-21 05-02-21 23-02-21 6
2.2.03.4 Tower-1-3rd Floor Slab 1672m2 100% 01-03-21 11-03-21 16-02-21 28-02-21 11
2.2.04.1 Tower-1-3rd Floor Column 31nos 100% 12-03-21 22-03-21 28-02-21 25-03-21 -3
2.2.04.2 Tower-1-3rd Floor Lift Core 2nos 100% 12-03-21 22-03-21 11-03-21 25-03-21 -3
2.2.04.3 Tower-1-3rd Floor Stair 2nos 100% 12-03-21 02-04-21 11-03-21 01-04-21 1
2.2.04.4 Tower-1-4th Floor Slab 1672m2 100% 23-03-21 02-04-21 11-03-21 01-04-21 1
2.2.05.1 Tower-1-4th Floor-Column 31nos 50% 03-04-21 13-04-21 22-06-21 22-06-21 -70 Completed
2.2.05.2 Tower-1-4th Floor-Lift Core 2nos % 03-04-21 13-04-21 0 Started
2.2.05.3 Tower-1-4th Floor-Stair 2nos % 03-04-21 24-04-21 0 Started
2.2.05.4 Tower-1-4th Floor-Roof Beam n Slab 1672m2 7% 14-04-21 24-04-21 22-06-21 22-06-21 -59 Completed
3.1.01 Tower-2-Pile Boring 156nos 100% 08-11-20 12-12-20 12-11-20 12-12-20 0
3.1.02 Tower-2-Pile Cap 17nos 100% 21-12-20 06-02-21 21-12-20 05-02-21 1
3.1.03 Tower-2-Short Column 17nos 100% 18-01-21 13-02-21 18-01-21 10-02-21 3
3.1.04 Tower-2-Lift Core below Grade Beam 1nos 100% 02-02-21 13-02-21 10-02-21 10-02-21 3
3.1.05 Tower-2-Grade Beam 192m 100% 03-02-21 05-03-21 23-02-21 02-03-21 3
3.2.01.1 Tower-2-GF Column 17nos 100% 05-04-21 15-05-21 13-03-21 25-03-21 51
3.2.01.2 Tower-2-GF Lift Core 1nos 100% 09-04-21 15-04-21 13-03-21 25-03-21 21
3.2.01.3 Tower-2-GF Stair 1nos 100% 09-04-21 26-04-21 25-03-21 19-04-21 7
3.2.01.4 Tower-2-1st Floor Slab 929m2 100% 16-04-21 26-04-21 12-04-21 19-04-21 7
3.2.02.1 Tower-2-1st Floor-Column 17nos 100% 27-04-21 07-05-21 28-04-21 26-09-21 -142
3.2.02.2 Tower-2-1st Floor-Lift Core 1nos 100% 01-05-21 07-05-21 29-04-21 26-09-21 -142
3.2.02.3 Tower-2-1st Floor-Stair 1nos 100% 01-05-21 28-05-21 04-05-21 21-09-21 -116
3.2.02.4 Tower-2-2nd Floor-Slab 1115m2 100% 08-05-21 28-05-21 29-04-21 26-09-21 -121
3.2.03.1 Tower-2-2nd Floor-Column 17nos 65% 02-10-21 12-10-21 30-09-21 21-02-22 -132 Completed
3.2.03.2 Tower-2-2nd Floor-Lift core 1no. 0% 06-10-21 12-10-21 0 Started
3.2.03.3 Tower-2-2nd Floor-Stair 1no. 0% 16-10-21 02-11-21 0 Started
3.2.03.4 Tower-2-3rd Floor Slab 929m2 30% 23-10-21 02-11-21 28-10-21 08-01-22 -67 Completed
4.1 Porch-Short Column nos 100% 21-01-21 29-01-21 27-01-21 27-01-21 2
4.2 Porch-Grade Beam m 100% 15-01-21 05-02-21 27-01-21 27-01-21 9
4.3 Porch-Column nos 100% 30-01-21 10-02-21 27-01-21 05-02-21 5
4.4 Porch-Beam and Slab 107m2 100% 11-02-21 18-02-21 07-02-21 07-02-21 11
5.01.1 Restaurant-GF Double Height Column 12nos 100% 28-02-21 10-03-21 28-02-21 25-03-21 -15
5.01.2 Restaurant-Porch Slab 223m2 100% 25-02-21 10-03-21 02-03-21 02-03-21 8
5.01.3 Restaurant-GF Double Height Roof Sl 557m2 100% 03-03-21 31-03-21 23-03-21 24-04-21 -24
5.02.1 Restaurant-2nd Floor-Column 12nos 100% 01-04-21 11-04-21 19-04-21 16-06-21 -66
5.02.2 Restaurant-2nd Floor-Roof Slab 836m2 67% 04-04-21 02-05-21 24-04-21 16-06-21 -45 Completed
6.1 Between Tower1-2-Short Column nos 100% 09-03-21 15-03-21 13-03-21 13-03-21 2
6.2 Between Tower1-2-Grade Beam m 100% 16-03-21 29-03-21 25-03-21 25-03-21 4
6.3 Between Tower1-2-Column nos 100% 30-03-21 12-04-21 11-04-21 11-04-21 1
6.4 Between Tower1-2-GF Roof Slab 372m2 100% 13-04-21 26-04-21 26-04-21 26-04-21 0
6.5 Between Tower-1-2-1st Flr Roof Slab 372m2 100% 27-04-21 10-05-21 05-06-21 05-06-21 -26
7.1 East Side Soak Well Slab 1no. 100% 10-01-22 27-01-22 27-01-22 27-01-22 0
7.2 West Side Septic Tank 1no. 25% 12-01-22 10-02-22 27-01-22 31-01-22 10 Completed
7.3 East Side Septic Tank 1no. 30% 21-01-22 19-02-22 27-01-22 10-02-22 9 Completed


DAILY MANPOWER








CUMMULATIVE ACTUAL WORK PROGRESS








CUMMULATIVE PLAN WORK PROGRESS








CUMMULATIVE WORK PROGRESS








SCHEDULE AHEAD-BEHIND






Site Photographs
on 18-09-20
on 18-09-20
on 6-11-20
on 6-11-20
Tower-1 Pile Cap on 12-11-20
Tower-2-Pile Work on 12-11-20
Tower-2-Piling Work on 28-11-20
Tower-1-Pile Cap Work on 28-11-20
Tower-1 Pile Cap on 30-11-20
Tower-1-Pilehead breaking on 30-11-20
Tower-1-Grade Beam on 4-12-20
Tower-2-Pile Work on 4-12-20
Column Work on 7-12-20
Tower-1 Grade Beam on 7-12-20
Tower-1-Excavation for Pile Cap on 9-12-20
Tower-2-Pile Work on 9-12-20
Tower-1-Pile Cap Re-bar Fabrication on 12-12-20
Tower-1-Pilecap Concreting on 12-12-20
Tower-1-Coliumn Re-bar work on 15-12-20
Tower-1-GF Beam Shuttering on 15-12-20
Tower-1-Grade Beam Re-bar Fabrication on 18-12-20
Tower-1-GF Beam Shuttering on 18-12-20
Tower-1-Lift Core Re-bar Work on 20-12-20
Tower-1-GF Slab Re-bar Work on 20-12-20
Tower-1-GF Roof Slab-2000 sft Concreting on 21-12-20
Tower-1-GF Roof Slab Concreting on 21-12-20
Tower-1-Grade Beam Shuttering on 24-12-20
Tower-2-Excavation for Pile Head Breakin on 24-12-20
Tower-1-GF Stair Shuttering on 27-12-20
Tower-2-Pile Head Breaking on 27-12-20
Tower-1-1st Floor Roof Slab Shuttering on 8-01-21
Tower-2-Pile Cap Concreting on 8-01-21
Tower-1-1st Floor Roof Slab 3600 sft Co on 11-01-21
Tower-1-1st Floor Roof Slab Concreting on 11-01-21
Tower-1-GF Roof Slab-3600sft Concreting on 16-01-21
Tower-1-GF Roof Slab Concreting on 16-01-21
Tower-1-GF Roof Slab 1800 sft Concreting on 18-01-21
Tower-1-1st Floor Roof Beam Shuttering on 18-01-21
Tower-1-GF Roof Slab-4250sft Concreting on 27-01-21
Tower-1-Lift Core and Slab Shuttering on 27-01-21
Tower-1-1st Floor Roof Slab 3600 sft Con on 5-02-21
Tower-2-GB Shutter Removing on 5-02-21
Tower-1-1st Floor Roof Slab 3600 sft Con on 7-02-21
Tower-1-1st Floor Roof Slab Concreting on 7-02-21
Tower-2-Grade Beam Shuttering on 10-02-21
Tower-1-1st floor Roof Slab 2450sft Conc on 10-02-21
Tower-1-2nd Floor Roof Slab-3600sft Conc on 16-02-21
Tower-2-Column Re-bar Work on 16-02-21
Tower-1-3rd Floor Column Re-bar Work on 23-02-21
Restaurant Area Slab Shutttering on 23-02-21
Tower-1-2nd Floor Roof Inspection on 25-02-21
Tower-1-2nd Floor Roof Curing on 25-02-21
Tower-1-3rd Floor Column Shuttering on 28-02-21
Resturant Area Slab Shuttering on 28-02-21
Restaurant-Double Height Slab Concreting on 2-03-21
Tower-1-3rd Floor Lift Core Re-bar Work on 2-03-21
Tower-1-3rd Floor Roof Slab Concreting on 11-03-21
View From South on 11-03-21
Tower-1-3rd Floor Roof Slab Shuttering on 13-03-21
Short Coulmn on 13-03-21
Restaurant GF Double Height Slab-6-9/A-B on 23-03-21
Tower-1-3rd Floor Roof Slab-Beam Shutter on 23-03-21
4th Floor Slab(3-5/B-E) Concreting-3600s on 24-03-21
Lift Core Wall Shuttering on 24-03-21
Tower-2: Lift Wall De-shuttering Work on 25-03-21
Column Shuttering Work on 25-03-21
Restaurant-GF Double Ht Roof Slab-Re-bar on 30-03-21
Tower-1-3rd Flr Roof Slab(B-E/5-6)Conret on 30-03-21
Tower-1-3rd Floor Roof Slab(B-E/6-7)Conc on 31-03-21
Tower-1-3rd Floor Roof Slab Curing on 31-03-21
Restaurant-GF Doubl Ht Roof Slab-Re-bar on 1-04-21
Tower-1-3rd Floor Roof Slab Curing on 1-04-21
on 11-04-21
on 11-04-21
Tower-2-Gr.Flr Roof Slab(5a-6/H-J) Concr on 12-04-21
on 12-04-21
on 19-04-21
Tower-1-GF Roof Slab(G-I/6-7a)Concreting on 19-04-21
Restaurant GF Doubl Ht Slab-1-4/A-B-Conc on 24-04-21
on 24-04-21
Between Tower1-2-GF Roof Slab-Conreting on 26-04-21
Lift Core Wall Shuttering on 26-04-21
Beam Shuttering on 28-04-21
Column Concreting on 28-04-21
Column Concreting on 29-04-21
Beam Shuttering on 29-04-21
Beam Shuttering Work on 30-04-21
Column Shuttering Work on 30-04-21
Roof Slab Shuttering on 2-05-21
Tower-2-Lift Core Deshuttering on 2-05-21
Roof Slab Shuttering on 4-05-21
Roof Slab Shuttering on 4-05-21
Roof Beam Shuttering on 9-05-21
Curing Work on 9-05-21
Restaurant GF Double Height Roof Slab on 24-05-21
Roof Slab De-shuttering on 24-05-21
Slab Shuttering on 31-05-21
Beam Shuttering on 31-05-21
Between Tower1-2-1st Flr Roof Slab-Concr on 5-06-21
Slab Re-bar Work on 5-06-21
Restaurant-3rd Floor Slab Concreting on 12-06-21
Restaurant-3rd Floor Slab Re-bar Work on 12-06-21
Restaurant-3rd Floor Slab Concreting on 16-06-21
Restaurant-3rd Floor Slab Concreting on 16-06-21
Grid:1-6/ A"-B=3300 sft
Tower-1-4th Floor Concreting on 22-06-21
Tower-2-2nd Floor Slab Shuttering on 22-06-21
Grid:5-8=877sft-West Verandhah Concreting
Tower-1-4th Floor Concreting on 26-06-21
Tower-2-2nd Floor Slab Shuttering on 26-06-21
Grid:1-4/A-B=90sft Slab Concreting
Tower-2:2nd floor slab re-bar work on 4-07-21
Tower-2:2nd floor slab concreting on 4-07-21
G-I/6-7a: 3300 sft
Tower-2:2nd floor slab concreting on 5-07-21
Tower-2-Column Rod binding-shuttering on 5-07-21
G-I/5a-6: 1500 sft
Tower-2:2nd flr double height slab concr on 26-09-21
Tower-2:2nd floor slab concreting on 26-09-21
5-8/I-K: 3200 sft
Tower-2-2nd Floor-Column Concreting on 30-09-21
Tower-2-2nd Floor-Column Concreting on 30-09-21
Tower-2 on 17-10-21
Tower-2-2nd Floor-Column Re-bar Work on 17-10-21
Tower-2-3rd Floor Slab Shutter Reparing on 28-10-21
Tower-2-2nd Floor Column Concreting on 28-10-21
Tower-2-3rd Flr Slab-Plain Sheet laying on 31-10-21
Tower-2-3rd Flor Slab-Rod Lifting on 31-10-21
Tower-2-3rd Floor Beam Re-bar work on 1-11-21
Tower-2-3rd Floor Beam Re-bar fabricatio on 1-11-21
Tower-2-3rd Floor Beam shuttering on 14-11-21
Tower-2-3rd Floor Beam shuttering on 14-11-21
Tower-2-3rd Floor Slab Shuttering on 30-11-21
Hollow box jointing for slab shuttering on 30-11-21
Tower-2-3rd Floor Slab-shuttering on 1-12-21
MS Prop Repairing on 1-12-21
Re-bar Fabrication on 31-12-21
Tower-2:3rd floor slab re-bar work on 31-12-21
Re-bar Fabricating on 1-01-22
Tower-2-3rd Floor-Re-bar Work on 1-01-22
Re-bar Cutting on 8-01-22
Tower-2-3rd Floor-Re-bar Work on 8-01-22
Septic Tank Wall Concreting on 27-01-22
Soak Well Slab Concreted on 27-01-22
Septic Tank Wall Curing on 31-01-22
Septic Tank Wall Plastering on 31-01-22
East Septic Tank Plastering on 1-02-22
East Septic Tank Plastering on 1-02-22
East Septic Tank Slab Shuttering on 10-02-22
East Septic Tank Slab Shuttering on 10-02-22
Column/Wall Steel Shutter Cleaning, Oili on 21-02-22
Column/Wall Steel Shutter Cleaning, Oili on 21-02-22