From 1-February-2022 to 21-February-2022
Project Code: 58Name:The View Hotel Kuakata
Client: Sikder Group Contractor:Cityscape International Ltd.
Progress as on: 21-February-2022
WBSWork Description
Total QuantityUpto 31-01-22This MonthTotal Done Schedule StartSchedule FinishActual Finish
3.2.03.1 Tower-2-2nd Floor-Column 17nos 60% 5% 65% 02-10-21 12-10-21 21-02-22
7.3 East Side Septic Tank 1no. 15% 15% 30% 21-01-22 19-02-22 10-02-22


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
East Septic Tank Plastering on 1-02-22East Septic Tank Plasteringon 1-02-22
East Septic Tank Slab Shuttering on 10-02-22East Septic Tank Slab Shutteringon 10-02-22
Column/Wall Steel Shutter Cleaning, Oili on 21-02-22Column/Wall Steel Shutter Cleaning, Oilion 21-02-22