MONTHLY PROGRESS REPORT |
From 1-February-2022 to 21-February-2022 | ||||
Project Code: | 58 | Name: | The View Hotel Kuakata | |
Client: | Sikder Group | Contractor: | Cityscape International Ltd. |
Progress as on: 21-February-2022 | ||||||||
WBS | Work Description | |||||||
Total Quantity | Upto 31-01-22 | This Month | Total Done | Schedule Start | Schedule Finish | Actual Finish | ||
3.2.03.1 | Tower-2-2nd Floor-Column | 17nos | 60% | 5% | 65% | 02-10-21 | 12-10-21 | 21-02-22 |
7.3 | East Side Septic Tank | 1no. | 15% | 15% | 30% | 21-01-22 | 19-02-22 | 10-02-22 |
Site Photographs | |
East Septic Tank Plastering on 1-02-22 | East Septic Tank Plasteringon 1-02-22 |
East Septic Tank Slab Shuttering on 10-02-22 | East Septic Tank Slab Shutteringon 10-02-22 |
Column/Wall Steel Shutter Cleaning, Oili on 21-02-22 | Column/Wall Steel Shutter Cleaning, Oilion 21-02-22 |