MONTHLY PROGRESS REPORT

From 1-November-2023 to 10-November-2023
Project Code: 21Name:New Hope Animal Nutrition Plant Bogura
Client: New Hope Contractor:Sarker Steel Ltd.
Progress as on: 10-November-2023
WBSWork Description
Total QuantityUpto 31-10-23This MonthTotal Done Schedule StartSchedule FinishActual Finish
3.1.5.1.5 Comp-GF-Floor Concreting 613m2 80% 20% 100% 10-07-23 16-07-23 02-11-23
3.1.5.1.6 Comp-GF-Tiles Fitting 790m2 70% 22% 92% 17-07-23 23-07-23 08-11-23
3.1.5.3 Comp-Outside Plastering m2 95% 5% 100% 28-07-23 11-08-23 02-11-23
3.1.6.1.2 Comp-GF-Plumbing work 1sum 50% 13% 63% 12-07-23 18-07-23 10-11-23
3.1.6.1.4 Comp-GF-Power Distribution Board nos 5% 55% 60% 19-07-23 25-07-23 06-11-23
3.1.6.2.2 Comp.1st Floor-Plumbing work 1sum 50% 13% 63% 04-08-23 08-08-23 10-11-23
3.1.6.2.4 Comp-1st Floor-Power Distribution Board nos 5% 55% 60% 05-08-23 11-08-23 06-11-23
3.2.4.3.1 Dormitory-2nd Floor-Column 12nos 36% 64% 100% 04-09-23 02-11-23 03-11-23
3.2.4.3.3 Dormotory-3rd Floor Slab-Formwork 240m2 0% 45% 45% 03-11-23 10-11-23 10-11-23
3.2.5.1.4 Canteen Dormitory-GF-Inside Plastering 468m2 40% 38% 78% 16-08-23 20-08-23 10-11-23
3.2.5.1.5 Canteen Dormitory-GF-Khoa-sand cushion 240m2 0% 40% 40% 16-08-23 20-08-23 10-11-23
3.2.6.1.1 Canteen Dormitory-GF-Sanitary Pipe work 1sum 0% 5% 5% 17-08-23 23-08-23 07-11-23
3.2.6.2.3 Dormitory-1st Floor-Electrical Pipe Work 1sum 0% 5% 5% 16-10-23 22-10-23 07-11-23
3.3.7.6 Gate House-Door Shutter, Window fixing 11nos 50% 50% 100% 25-08-23 26-08-23 03-11-23
3.3.7.7 Gate House-Painting m2 0% 10% 10% 09-10-23 15-10-23 09-11-23


MANPOWER HISTOGRAM








DAILY PROGRESS






Site Photographs
Dorm. Bldg. Ceiling Plaster on 1-11-23Comp. Bldg. GF Tiles work on 1-11-23
Dorm. Bldg. 2nd floor concreting work on 2-11-23Dorm. Bldg. Plaster work on 2-11-23
Dorm. Bldg. 2nd floor column work on 3-11-23Power cable laying work on 3-11-23
Dorm. Bldg. 2nd floor shuttering work on 6-11-23Sanitary group cutting on 6-11-23
Gate House Thai work on 7-11-23Gate House canopy on 7-11-23
Dorm. Bldg. 3rd floor slab shuttering on 8-11-23Gate roof top water proofing casting on 8-11-23
Dorm. Bldg. 3rd floor shuttering work on 9-11-23Dorm. Bldg. GF sand khoa cushion on 9-11-23
Dorm. Bldg. GF Concreting on 10-11-23Khoa laying at road on 10-11-23