DAILY PROGRES REPORT

Project:New Hope Animal Nutrition Plant Bogura Project Code: 21 Date10-November-2023
Client: New Hope Report216 DayFriday
Contractor:Sarker Steel Ltd. ClimateSunny
Temperature22-32C
Manpower
SNDescriptionNos
01SSL-Staff3
02Civil-Mason/ Mistry12
03Civil-Labor23
08Plumber/Electrician5
09Equipment Operator1
TOTAL 44
WBSWork Description Progress as on: 10-November-2023
Total QtyToday Done (%)Total Done (%)StartFinish
3.1.6.1.2 Comp-GF-Plumbing work 1sum 3 63 12-07-23 18-07-23
3.1.6.2.2 Comp.1st Floor-Plumbing work 1sum 3 63 04-08-23 08-08-23
3.2.4.3.3.1 Dormotory-3rd Floor Slab-Formwork 240m2 10 45 03-11-23 10-11-23
3.2.5.1.4 Canteen Dormitory-GF-Inside Plastering 468m2 3 78 16-08-23 20-08-23
3.2.5.1.5 Canteen Dormitory-GF-Khoa-sand cushion 240m2 25 40 16-08-23 20-08-23
Site Photographs
Dorm. Bldg. GF ConcretingKhoa laying at road
Site Description
Site Instruction