Return Main Menu

TOTAL PROGRES REPORT

From 16-March-2022 to 30-April-2022
Project Code: 19 Name: DPDC Sub-Station at Goran Dhaka
Client: DPDC Contractor:
Progress as on: 30-April-2022
Total Duration: 45 days Total Working Days: 3 Total Manpower: 61
Planning Progress = 95.8% Acual Progress = 95.8% SPI: 1 Ahead Schedule
WBS Work Description
Total Quantity Total Done Schedule Start Schedule Finish Actual Start Actual Finish Lead-Lag(day) Not Yet
01.1.1 Mobilization-Pile Gap Filling-Material 100% 09-03-22 09-03-22 16-03-22 16-03-22 -7
01.1.2 Mobilization-Pile Gap Filling-Labor 100% 10-03-22 10-03-22 16-03-22 16-03-22 -6
01.2.1 Other-Excavation upto 1st Bracing 0 100% 09-03-22 13-03-22 16-03-22 16-03-22 -3
01.2.2 Other-Excavation upto 2nd Bracing 0 100% 21-03-22 27-03-22 02-04-22 30-04-22 -34
01.2.3 Other-Excavation upto Mat 0 100% 04-04-22 10-04-22 30-04-22 30-04-22 -20
01.3.1.1 Bracing-1st Layer-Bracket Fixing 52nos 100% 14-03-22 15-03-22 16-03-22 02-04-22 -18
01.3.1.2 Bracing-1st Layer Installation 488m2 100% 16-03-22 20-03-22 16-03-22 30-04-22 -41
01.3.2.1 Bracing-2nd Layer-Bracket Fixing 52nos 100% 28-03-22 29-03-22 30-04-22 30-04-22 -32
01.3.2.2 Bracing-2nd Layer Installation 488m2 100% 30-03-22 03-04-22 30-04-22 30-04-22 -27
01.4.1 Pile Gap Filling upto 1st Bracing 154gap 100% 10-03-22 16-03-22 16-03-22 16-03-22 0
01.4.2 Pile Gap Filling upto 2nd Bracing 154gap 100% 28-03-22 03-04-22 30-04-22 30-04-22 -27
01.4.3 Pile Gap Filling upto Mat 154gap 100% 11-04-22 17-04-22 30-04-22 30-04-22 -13
01.5.1 Bracing Gap Filling-1st Bracing 106m 100% 01-04-22 03-04-22 02-04-22 02-04-22 1
01.5.2 Bracing Gap Filling-2nd Bracing 106m 0% 04-04-22 06-04-22 30-11--1 0 Started


DAILY MANPOWER








CUMMULATIVE ACTUAL WORK PROGRESS








CUMMULATIVE PLAN WORK PROGRESS








CUMMULATIVE WORK PROGRESS








SCHEDULE AHEAD-BEHIND






Site Photographs
Shore pile gap filling on 16-03-22
Shore pile Mortering on 16-03-22
Gap filling inbetween joist and cap beam on 2-04-22
Gap filling by mortering on 2-04-22
Water proofing work on 30-04-22
Pile gap water proofing on 30-04-22