RHD RATE SCHEDULE-2022 Updating.. | ||||
---|---|---|---|---|
Click on Code to see the analysis or Go Home | Profit=10%, Overhead=3.5%, VAT=5.5% | |||
16 | Earthwork | |||
Code | Item | Unit | Cost(Tk.) | Unit Rate(Tk.) |
1610000 | Erect Bumboo Profile Embankment | each | 324.00 |
398.13 |
1611010 | Earthwork Manual emb/bank/road 3m | cum | 203.00 |
248.82 |
1611020 | Earthwork Manual emb/bank/road 4m | cum | 217.00 |
266.84 |
1611030 | Earthwork Manual emb/bank/road 5m | cum | 232.00 |
284.93 |
1611040 | Earthwork Manual emb/bank/road 6m | cum | 247.00 |
302.74 |
1612010 | Construction Embankment 3m 85%com | cum | 239.00 |
292.68 |
1612020 | Construction Embankment 4m 85%com | cum | 253.00 |
310.70 |
1612030 | Construction Embankment 5m 85%com | cum | 268.00 |
328.78 |
1612040 | Construction Embankment 6m 85%com | cum | 283.00 |
346.80 |
1612050 | Construction Embankment 3m 90%com | cum | 257.00 |
315.11 |
1612060 | Construction Embankment 4m 90%com | cum | 271.00 |
333.13 |
1612070 | Construction Embankment 5m 90%com | cum | 286.00 |
351.22 |
1612080 | Construction Embankment 6m 90%com | cum | 301.00 |
369.24 |
1613010 | E/Work Manual Lab ManuaCompact-3m | cum | 248.00 |
304.06 |
1613020 | E/Work Manual Lab ManuaCompact-4m | cum | 262.00 |
322.08 |
1613030 | E/Work Manual Lab ManuaCompact-5m | cum | 277.00 |
340.24 |
1613040 | E/Work Manual Lab ManuaCompact-6m | cum | 292.00 |
358.19 |
1614010 | Compact Earth 80% Vibro Compactor | cum | 44.00 |
54.59 |
1614020 | Compact Earth by 7 kg Iron Rammer | cum | 45.00 |
55.24 |
1615010 | Compact Earth 85% 6m and above | cum | 36.00 |
43.86 |
1615020 | Compact Earth 90% 6m and above | cum | 54.00 |
66.29 |
1616000 | Extra Rate Additional Lead 15m | cum | 28.00 |
34.44 |
1617000 | Extra Rate Additional Lift 30cm | cum | 15.00 |
17.82 |
1618000 | Royality Earth from Private Land | cum | 18.00 |
22.09 |
1620010 | Earthwork carry Earth 300m-1km | cum | 403.00 |
494.24 |
1620020 | Earthwork carry 1-5km-Extra Rate | cum | 52.00 |
63.38 |
1621010 | E/work carry manual Comp-300m-1km | cum | 448.00 |
549.48 |
1621020 | E/work carry manual Comp-1-5km-Ex | cum | 52.00 |
63.38 |
1622010 | E/work cary earth85%Comp:300m-1km | cum | 406.00 |
497.84 |
1622020 | E/work cary earth85%Comp:1-5km-Ex | cum | 72.00 |
88.12 |
1622030 | E/work cary earth90%Comp:300m-1km | cum | 428.00 |
525.23 |
1622040 | E/work cary earth90%Comp:1-5km-Ex | cum | 85.00 |
103.82 |
1623010 | Embankment Mechanica Excavator-4m | cum | 141.00 |
173.49 |
1623020 | Embankment Mechanica Excavator>4m | cum | 170.00 |
208.29 |
1623580 | Clay cover 0-6m height 90% Compac | cum | 301.00 |
369.24 |
1624010 | Embankment Mech.Equip-4m 85%Compa | cum | 166.00 |
203.76 |
1624020 | Embk.Mech.Equip-4-6m,abov 85%Comp | cum | 192.00 |
235.95 |
1624030 | Embk.Mech.Equip-0-4m, 90% Compac | cum | 171.00 |
210.50 |
1624040 | Embk.Mech.Equip-4-6m,abov 90%Comp | cum | 198.00 |
242.69 |
1625010 | 300m-1km Embk:0-4m 85% Compaction | cum | 333.00 |
408.93 |
1625020 | 300m-1km Embk:4m above 85% Compac | cum | 360.00 |
441.11 |
1625030 | 300m-1km Embk:0-4m 90% Compaction | cum | 338.00 |
415.67 |
1625040 | 300m-1km Embk:4m above 90% Compac | cum | 365.00 |
447.86 |
1625050 | 1-5km Embk:0-4m 85% Compaction | cum | 405.00 |
497.05 |
1625060 | 1-5km Embk:4m abov 85% Compaction | cum | 431.00 |
529.24 |
1625070 | 1-5km Embk:0-4m 90% Compaction | cum | 410.00 |
503.79 |
1625080 | 1-5km Embk:4m abov 90% Compaction | cum | 437.00 |
535.98 |
1626010 | Borrow Earth Riverbed 1km 85%Comp | cum | 424.00 |
520.67 |
1626020 | Borrow Earth: 1-5km 85%Comp-Extra | cum | 72.00 |
88.12 |
1626030 | Borrow Earth Riverbed 1km 90%Comp | cum | 445.00 |
545.72 |
1626040 | Borrow Earth: 1-5km 90%Comp-Extra | cum | 85.00 |
103.82 |
1631010 | Clay Blanket/ core Head Load-300m | cum | 543.00 |
665.97 |
1631020 | Clay Blanket, truck/boat-300m-1km | cum | 520.00 |
625.61 |
1631030 | Clay Blanket, truck/boat-1-5km-Ex | cum | 49.00 |
60.03 |
1632010 | Caly Cover carry earth 0-1.00 km | cum | 525.00 |
644.35 |
1632020 | Caly Cover carry earth 1-5km-Extr | cum | 85.00 |
103.82 |
1632510 | Clay cover 0-3m height 85% Compac | cum | 239.00 |
292.68 |
1632520 | Clay cover 0-4m height 85% Compac | cum | 253.00 |
310.70 |
1632530 | Clay cover 0-5m height 85% Compac | cum | 268.00 |
328.78 |
1632540 | Clay cover 0-6m height 85% Compac | cum | 283.00 |
346.80 |
1632550 | Clay cover 0-3m height 90% Compac | cum | 257.00 |
315.11 |
1632560 | Clay cover 0-4m height 90% Compac | cum | 271.00 |
333.13 |
1632570 | Clay cover 0-5m height 90% Compac | cum | 286.00 |
351.22 |