BREAKDOWN OF UNIT PRICE |
Item:1632560. Clay cover 0-4m height 90% Compac |
Basis:1cum | |
22.Misc-2 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Diesel/ Fuel | 0.286 | ltr |
109.00 | |
|
|
Sub-Total(22) |
31.17
|
31.17
|
23.Misc-3 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Lubricant (Mobil Oil) | 0.014 | ltr |
500.00 | |
|
|
Sub-Total(23) |
7.00
|
7.00
|
70.Equipment-0 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
B.dozer/Roller/Comp:150HP | 0.002 | no. |
6900.00 | |
|
|
Sub-Total(70) |
13.80
|
13.80
|
83.Labour-3a |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Head Man | 0.002 | no. |
800.00 | |
|
Labour, Unskill/ Ordinary | 0.388 | no. |
550.00 | |
|
Misc. Sundry-Lab Unskill/ | 0.004 | no. |
550.00 | |
|
|
Sub-Total(83) |
217.20
|
217.20
|
84.Labour-4 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Operator, Dozer/Roler/Com | 0.002 | no. |
950.00 | |
|
|
Sub-Total(84) |
1.90
|
1.90
|
|
|
|
Total(1) |
|
271.07 |
|
Add over head on Total(1)
|
3.5 % |
9.49 |
|
Add Profit on Total(1) |
10.0 % |
27.11
|
|
|
|
Total(2) |
|
307.67 |
|
Add VAT on Unit Price |
7.5 % |
24.95 |
|
|
|
Unit Price |
|
332.62
|
|
|
|
Say |
333.13 |
per cum |