BREAKDOWN OF UNIT PRICE
Item:1611010. Earthwork Manual emb/bank/road 3m
Basis:1cum
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Head Man
0.002
no.
800.00
1.60
Labour, Unskill/ Ordinary
0.362
no.
550.00
199.10
Misc. Sundry-Lab Unskill/
0.004
no.
550.00
2.20
Sub-Total(83)
202.90
202.90
Total(1)
202.90
Add over head on Total(1)
3.5 %
7.10
Add Profit on Total(1)
10.0 %
20.29
Total(2)
230.29
Add VAT on Unit Price
7.5 %
18.67
Unit Price
248.96
Say
248.82
per cum