BREAKDOWN OF UNIT PRICE |
Item:1610000. Erect Bumboo Profile Embankment |
Basis:1no. | |
25.Misc-5 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Rope: Jute String | 0.250 | kg |
80.00 | |
|
|
Sub-Total(25) |
20.00
|
20.00
|
30.Wood Work-0 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Bamboo, 6 m, 51-60 mm Dia | 1.000 | No. |
235.00 | |
|
|
Sub-Total(30) |
235.00
|
235.00
|
83.Labour-3a |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Labour, Unskill/ Ordinary | 0.125 | no. |
550.00 | |
|
Misc. Sundry-Lab Unskill/ | 0.001 | no. |
550.00 | |
|
|
Sub-Total(83) |
69.30
|
69.30
|
|
|
|
Total(1) |
|
324.30 |
|
Add over head on Total(1)
|
3.5 % |
11.35 |
|
Add Profit on Total(1) |
10.0 % |
32.43
|
|
|
|
Total(2) |
|
368.08 |
|
Add VAT on Unit Price |
7.5 % |
29.84 |
|
|
|
Unit Price |
|
397.92
|
|
|
|
Say |
398.13 |
per each |