BREAKDOWN OF UNIT PRICE
Item:1246000. Labor Take out 40mm GI T/well Pip
Basis:1m
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Skilled
0.197
no.
600.00
118.20
Sub-Total(83)
118.20
118.20
85.Labour-5a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plumber
0.066
no.
700.00
46.20
Sub-Total(85)
46.20
46.20
Total(1)
164.40
Add over head on Total(1)
3.5 %
5.75
Add Profit on Total(1)
10.0 %
16.44
Total(2)
186.59
Add VAT on Unit Price
7.5 %
15.13
Unit Price
201.72
Say
201.23
per m