BREAKDOWN OF UNIT PRICE
Item:1218035. Install Dewateri T/wel 30m 150PVC
Basis:1no.
14.Material-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stone, Pea Gravel: 6mm
1.977
cum
3300.00
6524.10
Sub-Total(14)
6524.10
6524.10
22.Misc-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel/ Fuel
228.000
ltr
109.00
24852.00
Sub-Total(22)
24852.00
24852.00
23.Misc-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lubricant (Mobil Oil)
2.964
ltr
500.00
1482.00
Sub-Total(23)
1482.00
1482.00
30.Wood Work-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bamboo,Barak 7.5m,60-80mm
10.000
No.
320.00
3200.00
Sub-Total(30)
3200.00
3200.00
70.Equipment-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cargo Truck (Ex Fuel,Lub)
0.600
no.
5800.00
3480.00
Sub-Total(70)
3480.00
3480.00
71.Equipment-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Drilling Rig: 8 hrs/day
4.218
no.
4500.00
18981.00
Sub-Total(71)
18981.00
18981.00
73.Equipment-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
High Power Pump: 8hrs/day
1.000
no.
1730.00
1730.00
Electric Motor 25HP 2cuse
1.000
No.
37000.00
37000.00
Sub-Total(73)
38730.00
38730.00
75.Equipment-5
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
150mm Clas D PVC Strainer
15.000
m
1544.67
23170.05
150mm Clas C PVC Blind Pi
15.000
m
1051.00
15765.00
Sub-Total(75)
38935.05
38935.05
76.Equipment-6
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bail Plug, 100 mm dia
1.000
No.
1190.00
1190.00
Centrilizer, 13 mm dia
3.000
set
530.00
1590.00
Star-Delta Starter, MEM/
1.000
No.
3600.00
3600.00
Panel Board
1.000
No.
5000.00
5000.00
Sub-Total(76)
11380.00
11380.00
77.Equipment-7
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pipe GI 150mm dia 4mm Thk
3.000
m
2000.00
6000.00
Sub-Total(77)
6000.00
6000.00
78.Equipment-8
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
150mm dia Clas C PVC Pipe
20.000
m
1051.00
21020.00
Bend, GI 100 mm dia 4mm T
2.000
No.
2715.00
5430.00
Sub-Total(78)
26450.00
26450.00
79.Equipment-9
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Pipe Jointing Adhesiv
1.000
kg
280.00
280.00
Sub-Total(79)
280.00
280.00
81.Labour-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Rigman
21.093
no.
750.00
15819.75
Driller
4.218
no.
700.00
2952.60
Driller, Helper
4.218
no.
550.00
2319.90
Electrician
4.218
no.
700.00
2952.60
Sub-Total(81)
24044.85
24044.85
82.Labour-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Foreman
5.218
no.
850.00
4435.30
Sub-Total(82)
4435.30
4435.30
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Skilled
29.311
no.
600.00
17586.60
Labour, Unskill/ Ordinary
3.000
no.
550.00
1650.00
Misc. Sundry-Lab Unskill/
2.000
no.
550.00
1100.00
Sub-Total(83)
20336.60
20336.60
84.Labour-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mechanic
4.218
no.
700.00
2952.60
Sub-Total(84)
2952.60
2952.60
85.Labour-5a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Operator, Pump
1.000
no.
750.00
750.00
Sub-Total(85)
750.00
750.00
Total(1)
232813.50
Add over head on Total(1)
3.5 %
8148.47
Add Profit on Total(1)
10.0 %
23281.35
Total(2)
264243.32
Add VAT on Unit Price
7.5 %
21425.13
Unit Price
285668.46
Say
252126.26
per each