BREAKDOWN OF UNIT PRICE
Item:1218030. Install Dewateri T/wel 24m 150PVC
Basis:1no.
14.Material-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stone, Pea Gravel: 6mm
1.582
cum
3300.00
5220.60
Sub-Total(14)
5220.60
5220.60
22.Misc-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel/ Fuel
184.800
ltr
109.00
20143.20
Sub-Total(22)
20143.20
20143.20
23.Misc-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lubricant (Mobil Oil)
2.405
ltr
500.00
1202.50
Sub-Total(23)
1202.50
1202.50
30.Wood Work-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bamboo,Barak 7.5m,60-80mm
10.000
No.
320.00
3200.00
Sub-Total(30)
3200.00
3200.00
70.Equipment-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cargo Truck (Ex Fuel,Lub)
0.600
no.
5800.00
3480.00
Sub-Total(70)
3480.00
3480.00
71.Equipment-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Drilling Rig: 8 hrs/day
3.374
no.
4500.00
15183.00
Sub-Total(71)
15183.00
15183.00
73.Equipment-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
High Power Pump: 8hrs/day
1.000
no.
1730.00
1730.00
Electric Motor 25HP 2cuse
1.000
No.
37000.00
37000.00
Sub-Total(73)
38730.00
38730.00
75.Equipment-5
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
150mm Clas D PVC Strainer
12.000
m
1544.67
18536.04
150mm Clas C PVC Blind Pi
12.000
m
1051.00
12612.00
Sub-Total(75)
31148.04
31148.04
76.Equipment-6
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Centrilizer, 13 mm dia
3.000
set
530.00
1590.00
Star-Delta Starter, MEM/
1.000
No.
3600.00
3600.00
Panel Board
1.000
No.
5000.00
5000.00
Sub-Total(76)
10190.00
10190.00
77.Equipment-7
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pipe GI 150mm dia 4mm Thk
3.000
m
2000.00
6000.00
Sub-Total(77)
6000.00
6000.00
78.Equipment-8
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
150mm dia Clas C PVC Pipe
20.000
m
1051.00
21020.00
Bend, GI 100 mm dia 4mm T
2.000
No.
2715.00
5430.00
Sub-Total(78)
26450.00
26450.00
79.Equipment-9
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Pipe Jointing Adhesiv
1.000
kg
280.00
280.00
Sub-Total(79)
280.00
280.00
81.Labour-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Rigman
16.874
no.
750.00
12655.50
Driller
3.374
no.
700.00
2361.80
Driller, Helper
3.374
no.
550.00
1855.70
Electrician
3.374
no.
700.00
2361.80
Sub-Total(81)
19234.80
19234.80
82.Labour-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Foreman
4.374
no.
850.00
3717.90
Sub-Total(82)
3717.90
3717.90
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Skilled
21.249
no.
600.00
12749.40
Labour, Unskill/ Ordinary
3.000
no.
550.00
1650.00
Misc. Sundry-Lab Unskill/
2.000
no.
550.00
1100.00
Sub-Total(83)
15499.40
15499.40
84.Labour-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mechanic
3.374
no.
700.00
2361.80
Sub-Total(84)
2361.80
2361.80
85.Labour-5a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Operator, Pump
1.000
no.
750.00
750.00
Sub-Total(85)
750.00
750.00
Total(1)
202791.24
Add over head on Total(1)
3.5 %
7097.69
Add Profit on Total(1)
10.0 %
20279.12
Total(2)
230168.06
Add VAT on Unit Price
7.5 %
18662.27
Unit Price
248830.33
Say
212590.61
per each