BREAKDOWN OF UNIT PRICE
Item:1218025. Install Dewateri T/wel 18m 150PVC
Basis:1no.
14.Material-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stone, Pea Gravel: 6mm
1.186
cum
3300.00
3913.80
Sub-Total(14)
3913.80
3913.80
22.Misc-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel/ Fuel
90.000
ltr
109.00
9810.00
Sub-Total(22)
9810.00
9810.00
23.Misc-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lubricant (Mobil Oil)
1.172
ltr
500.00
586.00
Sub-Total(23)
586.00
586.00
30.Wood Work-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bamboo,Barak 7.5m,60-80mm
10.000
No.
320.00
3200.00
Sub-Total(30)
3200.00
3200.00
70.Equipment-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cargo Truck (Ex Fuel,Lub)
0.300
no.
5800.00
1740.00
Sub-Total(70)
1740.00
1740.00
71.Equipment-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Tripod Drilling Set-Coplt
2.000
no.
5500.00
11000.00
Sub-Total(71)
11000.00
11000.00
73.Equipment-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Electric Motor 20HP 2cuse
1.000
No.
29000.00
29000.00
Sub-Total(73)
29000.00
29000.00
75.Equipment-5
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
150mm Clas D PVC Strainer
9.000
m
1544.67
13902.03
150mm Clas C PVC Blind Pi
9.000
m
1051.00
9459.00
Sub-Total(75)
23361.03
23361.03
76.Equipment-6
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Centrilizer, 13 mm dia
3.000
set
530.00
1590.00
Star-Delta Starter, MEM/
1.000
No.
3600.00
3600.00
Panel Board
1.000
No.
5000.00
5000.00
Sub-Total(76)
10190.00
10190.00
77.Equipment-7
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pipe GI 150mm dia 4mm Thk
3.000
m
2000.00
6000.00
Sub-Total(77)
6000.00
6000.00
78.Equipment-8
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
150mm dia Clas C PVC Pipe
20.000
m
1051.00
21020.00
Bend, GI 100 mm dia 4mm T
2.000
No.
2715.00
5430.00
Sub-Total(78)
26450.00
26450.00
79.Equipment-9
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Pipe Jointing Adhesiv
1.000
kg
280.00
280.00
Sub-Total(79)
280.00
280.00
81.Labour-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Driller
2.000
no.
700.00
1400.00
Driller, Helper
3.000
no.
550.00
1650.00
Electrician
2.000
no.
700.00
1400.00
Sub-Total(81)
4450.00
4450.00
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Skilled
6.500
no.
600.00
3900.00
Labour, Unskill/ Ordinary
13.000
no.
550.00
7150.00
Misc. Sundry-Lab Unskill/
2.000
no.
550.00
1100.00
Sub-Total(83)
12150.00
12150.00
84.Labour-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mechanic
0.400
no.
700.00
280.00
Mechanic, Helper
0.600
no.
590.00
354.00
Sub-Total(84)
634.00
634.00
85.Labour-5a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Operator, Pump
6.500
no.
750.00
4875.00
Sub-Total(85)
4875.00
4875.00
Total(1)
147639.83
Add over head on Total(1)
3.5 %
5167.39
Add Profit on Total(1)
10.0 %
14763.98
Total(2)
167571.21
Add VAT on Unit Price
7.5 %
13586.85
Unit Price
181158.06
Say
148220.23
per each