BREAKDOWN OF UNIT PRICE
Item:1218020. Install Dewateri T/wel 18m 100PVC
Basis:1no.
14.Material-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stone, Pea Gravel: 6mm
0.919
cum
3300.00
3032.70
Sub-Total(14)
3032.70
3032.70
22.Misc-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel/ Fuel
90.000
ltr
109.00
9810.00
Sub-Total(22)
9810.00
9810.00
23.Misc-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lubricant (Mobil Oil)
1.172
ltr
500.00
586.00
Sub-Total(23)
586.00
586.00
30.Wood Work-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bamboo,Barak 7.5m,60-80mm
10.000
No.
320.00
3200.00
Sub-Total(30)
3200.00
3200.00
47.Steel-7
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wire GI 12 BWG
2.000
kg
120.00
240.00
Sub-Total(47)
240.00
240.00
70.Equipment-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cargo Truck (Ex Fuel,Lub)
0.300
no.
5800.00
1740.00
Sub-Total(70)
1740.00
1740.00
71.Equipment-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Tripod Drilling Set-Coplt
1.500
no.
5500.00
8250.00
Sub-Total(71)
8250.00
8250.00
75.Equipment-5
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
100mm Clas D PVC Strainer
9.000
m
692.65
6233.85
100mm Clas C PVC Blind Pi
9.000
m
421.00
3789.00
Sub-Total(75)
10022.85
10022.85
76.Equipment-6
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Centrilizer, 13 mm dia
3.000
set
530.00
1590.00
Disel Operat Engin-1 cuse
1.000
No.
32500.00
32500.00
Sub-Total(76)
34090.00
34090.00
77.Equipment-7
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pipe GI 100mm dia 5mm Thk
3.000
m
2100.00
6300.00
Sub-Total(77)
6300.00
6300.00
78.Equipment-8
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
100mm dia Clas C PVC Pipe
10.000
m
421.00
4210.00
Bend, GI 100 mm dia
2.000
No.
603.00
1206.00
Sub-Total(78)
5416.00
5416.00
79.Equipment-9
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Pipe Jointing Adhesiv
1.000
kg
280.00
280.00
Sub-Total(79)
280.00
280.00
81.Labour-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Driller
1.500
no.
700.00
1050.00
Driller, Helper
2.250
no.
550.00
1237.50
Sub-Total(81)
2287.50
2287.50
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Skilled
5.500
no.
600.00
3300.00
Labour, Unskill/ Ordinary
12.000
no.
550.00
6600.00
Misc. Sundry-Lab Unskill/
2.000
no.
550.00
1100.00
Sub-Total(83)
11000.00
11000.00
84.Labour-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mechanic
0.300
no.
700.00
210.00
Mechanic, Helper
0.500
no.
590.00
295.00
Sub-Total(84)
505.00
505.00
85.Labour-5a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Operator, Pump
5.500
no.
750.00
4125.00
Sub-Total(85)
4125.00
4125.00
Total(1)
100885.05
Add over head on Total(1)
3.5 %
3530.98
Add Profit on Total(1)
10.0 %
10088.51
Total(2)
114504.53
Add VAT on Unit Price
7.5 %
9284.15
Unit Price
123788.68
Say
98728.78
per each