BREAKDOWN OF UNIT PRICE
Item:1218010. Install Dewateri T/wel 18m 75 PVC
Basis:1no.
14.Material-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Stone, Pea Gravel: 6mm
0.552
cum
3300.00
1821.60
Sub-Total(14)
1821.60
1821.60
22.Misc-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel/ Fuel
90.000
ltr
109.00
9810.00
Sub-Total(22)
9810.00
9810.00
23.Misc-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lubricant (Mobil Oil)
1.172
ltr
500.00
586.00
Sub-Total(23)
586.00
586.00
30.Wood Work-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bamboo,Barak 7.5m,60-80mm
10.000
No.
320.00
3200.00
Sub-Total(30)
3200.00
3200.00
47.Steel-7
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wire GI 12 BWG
2.000
kg
120.00
240.00
Sub-Total(47)
240.00
240.00
70.Equipment-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cargo Truck (Ex Fuel,Lub)
0.300
no.
5800.00
1740.00
Sub-Total(70)
1740.00
1740.00
71.Equipment-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Tripod Drilling Set-Coplt
1.000
no.
5500.00
5500.00
Sub-Total(71)
5500.00
5500.00
75.Equipment-5
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
75mm Clas D PVC Strainer
9.000
m
418.00
3762.00
75mm Clas C PVC Blind Pip
9.000
m
281.00
2529.00
Sub-Total(75)
6291.00
6291.00
76.Equipment-6
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Centrilizer, 13 mm dia
3.000
set
530.00
1590.00
Disel Operat Engin-1 cuse
1.000
No.
32500.00
32500.00
Sub-Total(76)
34090.00
34090.00
77.Equipment-7
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pipe GI 75 mm dia 5mm Thk
3.000
m
1400.00
4200.00
Sub-Total(77)
4200.00
4200.00
78.Equipment-8
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
75mm dia Clas C PVC Pipe
10.000
m
281.00
2810.00
Bend, GI 75 mm dia
2.000
No.
416.00
832.00
Sub-Total(78)
3642.00
3642.00
79.Equipment-9
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Pipe Jointing Adhesiv
1.000
kg
280.00
280.00
Sub-Total(79)
280.00
280.00
81.Labour-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Driller
1.000
no.
700.00
700.00
Driller, Helper
1.500
no.
550.00
825.00
Sub-Total(81)
1525.00
1525.00
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Skilled
4.500
no.
600.00
2700.00
Labour, Unskill/ Ordinary
11.000
no.
550.00
6050.00
Misc. Sundry-Lab Unskill/
2.000
no.
550.00
1100.00
Sub-Total(83)
9850.00
9850.00
84.Labour-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mechanic
0.300
no.
700.00
210.00
Mechanic, Helper
0.500
no.
590.00
295.00
Sub-Total(84)
505.00
505.00
85.Labour-5a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Operator, Pump
5.000
no.
750.00
3750.00
Sub-Total(85)
3750.00
3750.00
Total(1)
87030.60
Add over head on Total(1)
3.5 %
3046.07
Add Profit on Total(1)
10.0 %
8703.06
Total(2)
98779.73
Add VAT on Unit Price
7.5 %
8009.17
Unit Price
106788.90
Say
83416.19
per each