BREAKDOWN OF UNIT PRICE
Item:0815040. Carriag Material Boat 2nd km abov
Basis:1cum
22.Misc-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel/ Fuel
0.094
ltr
109.00
10.25
Sub-Total(22)
10.25
10.25
23.Misc-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lubricant (Mobil Oil)
0.005
ltr
500.00
2.50
Sub-Total(23)
2.50
2.50
80.Laboor-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Boat, Engine
0.010
no.
1760.00
17.60
Sub-Total(80)
17.60
17.60
Total(1)
30.35
Add over head on Total(1)
3.5 %
1.06
Add Profit on Total(1)
10.0 %
3.03
Total(2)
34.44
Add VAT on Unit Price
7.5 %
2.79
Unit Price
37.24
Say
36.96
per m3/k