BREAKDOWN OF UNIT PRICE
Item:0812010. Carriage Material Boat within 1km
Basis:1m
22.Misc-2
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel/ Fuel
0.091
ltr
109.00
9.92
Sub-Total(22)
9.92
9.92
23.Misc-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Lubricant (Mobil Oil)
0.005
ltr
500.00
2.50
Sub-Total(23)
2.50
2.50
80.Laboor-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Boat, Engine
0.017
no.
1760.00
29.92
Sub-Total(80)
29.92
29.92
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Unskill/ Ordinary
0.505
no.
550.00
277.75
Sub-Total(83)
277.75
277.75
Total(1)
320.09
Add over head on Total(1)
3.5 %
11.20
Add Profit on Total(1)
10.0 %
32.01
Total(2)
363.30
Add VAT on Unit Price
7.5 %
29.46
Unit Price
392.76
Say
392.67
per m/km