BREAKDOWN OF UNIT PRICE
Item:0462020. Fill Expn Jnt sand,bitu-40mm-20mm
Basis:1m
13.Material-3
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand, FM>=2.5
0.001
cum
1900.00
1.90
Sub-Total(13)
1.90
1.90
21.Misc-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bitumen: 80/100
0.433
kg
87.00
37.67
Sub-Total(21)
37.67
37.67
34.Wood-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood, Fire
0.525
kg
5.90
3.10
Sub-Total(34)
3.10
3.10
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Skilled
0.020
no.
600.00
12.00
Labour, Unskill/ Ordinary
0.040
no.
550.00
22.00
Sub-Total(83)
34.00
34.00
Total(1)
76.67
Add over head on Total(1)
3.5 %
2.68
Add Profit on Total(1)
10.0 %
7.67
Total(2)
87.02
Add VAT on Unit Price
7.5 %
7.06
Unit Price
94.07
Say
93.25
per m