BREAKDOWN OF UNIT PRICE
Item:0421020. Supply, fix Wood Gauge 100x25mm
Basis:1m
24.Misc-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Paint, Ready Mixed
0.015
ltr
270.00
4.05
Sub-Total(24)
4.05
4.05
35.Wood-5
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood, Season, Shil Karai
0.003
cum
88200.00
264.60
Sub-Total(35)
264.60
264.60
80.Laboor-0
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Carpnter
0.284
no.
700.00
198.80
Carpenter, Helper
0.034
no.
550.00
18.70
Sub-Total(80)
217.50
217.50
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Unskill/ Ordinary
0.011
no.
550.00
6.05
Sub-Total(83)
6.05
6.05
85.Labour-5a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Painter/ Varnisher
0.014
no.
700.00
9.80
Sub-Total(85)
9.80
9.80
Total(1)
502.00
Add over head on Total(1)
3.5 %
17.57
Add Profit on Total(1)
10.0 %
50.20
Total(2)
569.77
Add VAT on Unit Price
7.5 %
46.20
Unit Price
615.97
Say
571.98