BREAKDOWN OF UNIT PRICE
Item:0418000. Prepartion Site, remove soil-15cm
Basis:1sqm
83.Labour-3a
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour, Unskill/ Ordinary
0.053
no.
550.00
29.15
Sub-Total(83)
29.15
29.15
84.Labour-4
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.005
no.
700.00
3.50
Mason, Head
0.000
no.
800.00
0.00
Mason, Helper
0.005
no.
590.00
2.95
Sub-Total(84)
6.45
6.45
Total(1)
35.60
Add over head on Total(1)
3.5 %
1.25
Add Profit on Total(1)
10.0 %
3.56
Total(2)
40.41
Add VAT on Unit Price
7.5 %
3.28
Unit Price
43.68
Say
44.52
per Sqm