RHD RATE SCHEDULE-2022 Updating.. | ||||
---|---|---|---|---|
Click on Code to see the analysis or Go Home | Profit=10%, Overhead=3.5%, VAT=5.5% | |||
02 | EARTHR_WORKS | |||
Code | Item | Unit | Cost(Tk.) | Unit Rate(Tk.) |
020101 | Clearing and Grubbing | Sqm | 52.00 |
62 |
020102A | Remove and uproot trees of different girth measured one meter above ground level, if the tree is more than two-meter-high, falling within the Right of Way, and remove sub surface roots, transport and dispose off Site to Contractor’s tip. Trees with girth 300 mm to 800 mm | Nos | 880.00 |
1057 |
020102B | Remove Trees with girth 801 mm to 1500 mm | Nos | 1460.00 |
1754 |
020102C | Remove Trees with girth from 1501 mm and above | Nos. | 3520.00 |
4228 |
020201 | Roadway Excavation in Unsuitable Soil Cubic Metre including stockpiling or disposal in a location agreed by Engineer | Cum | 186.00 |
223 |
020202 | Roadway Excavation in Suitable Soil including stockpiling on Site | Cum | 131.00 |
157 |
020203A | Roadway Excavation in Asphaltic Concrete by Milling Machine | Cum | 289.00 |
347 |
020203B | Roadway excavation in Aggregate Base | Cum | 141.00 |
169 |
020203C | Roadway excavation in sub base (Bricks Agg) | Cum | 141.00 |
169 |
020203D | Roadway Excavation in Existing Reinforced Concrete Pavement | Cum | 1286.00 |
1545 |
020204A | Deduction for Value of Roadway Excavationin Asphaltic Concrete | Cum | 3965.00 |
4762 |
020204B | Deduction for Value of Roadway Excavation in Aggregate Base | Cum | 3053.00 |
3667 |
020204C | Deduction for value of Roadway excavation in sub base (Bricks Agg) | Cum | 1455.00 |
1748 |
020204D | Deduction for Value of Roadway Excavation in Suitable Soil | Cum | 207.00 |
249 |
020401 | Channel Excavation in suitable/Unsuitable Materials | Cum | 199.00 |
239 |
020501 | Excavation and Backfill for Structures | Cum | 423.00 |
508 |
020601A | Embankment Fill From Suitable Roadway Excavation on Site | Cum | 131.00 |
157 |
020601B | Embankment Fill from River Bed Materials Supplied by Contractors Own Arrangement | Cum | 334.00 |
401 |
020602 | Sand Backfill to Swamp | Cum | 301.00 |
362 |
020603 | Cladding Layer | Cum | 415.00 |
498 |
020604 | Construction of Pore water release valve including supply of all materials and Labour as per drawings | No. | 4870.00 |
5849 |
020701 | Preparation of subgrade surface (300 mm) excess. Item 2/6/1c will include the material and other cost | Sqm | 22.00 |
26 |
020801 | Improved Subgrade | Cum | 949.00 |
1140 |
020901 | Dismantling existing Structure (Box culvert/Pipe culvert/Bridge) including disposal of spoil and backfilling (Individual Structure to be stated in Bill of Quantities) | Cum | 3766.00 |
4523 |
020902 | Cum | 3571.00 |
4289 |
|
020903A | Deduction of the Value of Recovered Materials (Except Reinforcing steel) from Structures | Cum | 943.00 |
1133 |
020903B | Deduction of the Value of Recovered Materials(Reinforcing Steel) from Structures | Ton | 15020.00 |
18040 |
021001 | Construction of Soil Earthen Shoulders | Cum | 190.00 |
228 |
021301 | Provide dikes to cross-sectional area including dewatering as instructed | Cum | 377.00 |
453 |
021302 | Supply and install 8-20 m long PVD drains as detailed design or instructed by the Engineer | m | 137.00 |
165 |
021303 | Supply and Laying geo-textile fabric in accordance with drawings and specification | Sqm | 149.00 |
179 |
021304 | Construction of vertical drain | m | 672.00 |
807 |
021305 | Supply, install and monitoring settlement plates complete with rods at levels and locations as instructed | no. | 7661.00 |
9201 |
021306 | Supply, install and monitoring VW piezometers | no. | 37900.00 |
45520 |
021307 | Supply and apply of surcharge materials for stabilizing soft ground. (materials will be reused) | Cum | 180.00 |
216 |
021308A | Secondary sub-soil investigation (including SPT, soil profile and classification, natural moisture content, shear (un-drained, and consolidated un-drained) and consolidation parameters Borehole 10-15m depth (Road and culvert) | nos. | 25100.00 |
30147 |
021308B | nos. | 35100.00 |
42157 |
|
021308C | Borehole 75-90m depth (Bridge and Overpass) | nos | 370000.00 |
444392 |
021309 | Supply and laying drainage blanket material in accordance with the drawings and specification | Cum | 2244.00 |
2695 |