BREAKDOWN OF UNIT PRICE
Item:060804. New Jersey Barrier
Basis:3rft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
4.000
day
60.00
240.00
Concrete Mixer (7/5)
1.000
day
2300.00
2300.00
Sub-Total(A1)
2540.00
2540.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
1.000
pers
700.00
700.00
Labour-Un-skilled
3.000
pers
540.00
1620.00
Sub-Total(B1)
2320.00
2320.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coarse Sand FM > 2.5
0.380
cum
1836.00
697.68
Cement - OPC
0.410
Ton
8800.00
3608.00
Reinforcing Bar Grade 60
0.059
Ton
72000.00
4248.00
Crushed Boulder/Gravel<25
0.350
cum
7250.00
2537.50
G.I. Wire. nails etc
0.030
kg
120.00
3.60
Wooden Shutter-use 6 time
18.520
sqm
200.00
3704.00
Sub-Total(C1)
14798.78
14798.78
Total(1)
19658.78
Add over head on Total(1)
3.5 %
688.06
Add Profit on Total(1)
10.0 %
1965.88
Total(2)
2653.94
Add VAT on Unit Price
5.5 %
154.46
Unit Price
2808.40
Say
2808
per m