BREAKDOWN OF UNIT PRICE
Item:060501. Road Marking Thermoplas-Spray-3mm
Basis:3767sft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Truck (5 Tonne)
1.000
day
8000.00
8000.00
Boiler/Heater (1)
1.000
day
9200.00
9200.00
Spreader
1.000
day
9200.00
9200.00
Sub-Total(A1)
26400.00
75.43
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Foreman
3.000
pers
850.00
2550.00
Labour-Skilled
7.000
pers
580.00
4060.00
Labour-Un-skilled
10.000
pers
540.00
5400.00
Sub-Total(B1)
12010.00
34.31
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Tharmoplastic Materials
2100.000
kg
121.40
254940.00
Glass Beads
175.000
kg
121.40
21245.00
Chalk Powder. brush etc.
1.000
LS
500.00
500.00
Sub-Total(C1)
276685.00
790.53
Total(1)
900.27
Add over head on Total(1)
3.5 %
31.51
Add Profit on Total(1)
10.0 %
90.03
Total(2)
121.54
Add VAT on Unit Price
5.5 %
7.07
Unit Price
128.61
Say
129
per Sqm