BREAKDOWN OF UNIT PRICE
Item:060401A. Median with Both sidePC Kerb-5.0m
Basis:7rft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
4.000
day
60.00
240.00
Sub-Total(A1)
240.00
120.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
1.000
pers
560.00
560.00
Labour-Un-skilled
2.000
pers
540.00
1080.00
Sub-Total(B1)
1640.00
820.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
0.253
cum
730.00
184.69
Cement - OPC
0.150
Ton
8800.00
1320.00
Pre-cast Kerb
10.000
pcs
85.00
850.00
Sub-Total(C1)
2354.69
1177.35
Total(1)
2117.35
Add over head on Total(1)
3.5 %
74.11
Add Profit on Total(1)
10.0 %
211.73
Total(2)
285.84
Add VAT on Unit Price
5.5 %
16.64
Unit Price
302.48
Say
302
per m