Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:060305G. RCC U-shape Cover Drain-1000-1500
Basis:3rft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
2.000
day
60.00
120.00
Concrete Mixer (7/5)
0.250
day
2300.00
575.00
Excavator
0.250
day
13000.00
3250.00
Sub-Total(A1)
3945.00
3945.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.250
pers
700.00
175.00
Labour-Un-skilled
0.500
pers
540.00
270.00
Sub-Total(B1)
445.00
445.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coarse Sand FM > 2.5
0.144
cum
1836.00
264.38
Cement - OPC
0.099
Ton
8800.00
871.20
Reinforcing Bar Grade 60
0.043
Ton
72000.00
3096.00
Crushed Boulder/Gravel<25
0.160
cum
7250.00
1160.00
G.I. Wire. nails etc
0.010
kg
120.00
1.20
Wooden Shutter-use 6 time
4.000
sqm
200.00
800.00
Sub-Total(C1)
6192.78
6192.78
Total(1)
10582.78
Add over head on Total(1)
3.5 %
370.40
Add Profit on Total(1)
10.0 %
1058.28
Total(2)
1428.68
Add VAT on Unit Price
5.5 %
83.15
Unit Price
1511.83
Say
1512
per m