BREAKDOWN OF UNIT PRICE
Item:060305E. RCC Drianage Pipe-300 mm dia
Basis:3kg.
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
0.750
day
60.00
45.00
Sub-Total(A1)
45.00
13715.33
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.250
pers
700.00
175.00
Labour-Un-skilled
0.500
pers
540.00
270.00
Sub-Total(B1)
445.00
135629.38
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Pipe 300 mm dia
1.000
m
550.00
550.00
Cement Concrete Class 20
0.024
cum
14003.00
336.07
Sub-Total(C1)
886.07
270061.57
Total(1)
419406.28
Add over head on Total(1)
3.5 %
14679.22
Add Profit on Total(1)
10.0 %
41940.63
Total(2)
56619.85
Add VAT on Unit Price
5.5 %
3295.34
Unit Price
59915.18
Say
59915
per m