BREAKDOWN OF UNIT PRICE
Item:060305D. Concrete Chute Drain-Rural High E
Basis:3rft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
3.000
day
60.00
180.00
Concrete Mixer (7/5)
0.120
day
2300.00
276.00
Sub-Total(A1)
456.00
456.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
0.250
pers
560.00
140.00
Labour-Un-skilled
0.750
pers
540.00
405.00
Sub-Total(B1)
545.00
545.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
0.006
cum
730.00
4.38
Cement - OPC
0.006
Ton
8800.00
52.80
Crushed Boulder/Gravel<25
0.020
cum
7250.00
145.00
Wooden Shutter-use 6 time
0.215
sqm
200.00
43.00
Sub-Total(C1)
245.18
245.18
Total(1)
1246.18
Add over head on Total(1)
3.5 %
43.62
Add Profit on Total(1)
10.0 %
124.62
Total(2)
168.23
Add VAT on Unit Price
5.5 %
9.79
Unit Price
178.03
Say
178
per m