BREAKDOWN OF UNIT PRICE
Item:060305C. U-shaped Covered Surface Drain
Basis:3rft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
4.000
day
60.00
240.00
Concrete Mixer (7/5)
1.000
day
2300.00
2300.00
Sub-Total(A1)
2540.00
2540.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
1.000
pers
700.00
700.00
Labour-Un-skilled
2.000
pers
540.00
1080.00
Sub-Total(B1)
1780.00
1780.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coarse Sand FM > 2.5
0.057
cum
1836.00
104.65
Cement - OPC
0.042
Ton
8800.00
369.60
Reinforcing Bar Grade 60
0.035
Ton
72000.00
2520.00
Crushed Boulder/Gravel<25
0.067
cum
7250.00
485.75
G.I. Wire. nails etc
0.008
kg
120.00
0.96
Wooden Shutter-use 6 time
1.200
sqm
200.00
240.00
Sub-Total(C1)
3720.96
3720.96
Total(1)
8040.96
Add over head on Total(1)
3.5 %
281.43
Add Profit on Total(1)
10.0 %
804.10
Total(2)
1085.53
Add VAT on Unit Price
5.5 %
63.18
Unit Price
1148.71
Say
1149
per m