BREAKDOWN OF UNIT PRICE
Item:060305B. Catch Pit with Steel Grating
Basis:1no.
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
3.000
day
60.00
180.00
Sub-Total(A1)
180.00
180.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Skilled
1.000
pers
580.00
580.00
Labour-Un-skilled
2.000
pers
540.00
1080.00
Sub-Total(B1)
1660.00
1660.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
0.153
cum
730.00
111.69
Cement - OPC
0.108
Ton
8800.00
950.40
1st Class Brick
240.000
Nos.
10.00
2400.00
Steel Grating
1.000
no.
320.00
320.00
Sub-Total(C1)
3782.09
3782.09
Total(1)
5622.09
Add over head on Total(1)
3.5 %
196.77
Add Profit on Total(1)
10.0 %
562.21
Total(2)
758.98
Add VAT on Unit Price
5.5 %
44.17
Unit Price
803.16
Say
803
per Nos.