BREAKDOWN OF UNIT PRICE
Item:060301. Manhole Complete as per drawing
Basis:1no.
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (2)
2.000
day
60.00
120.00
Sub-Total(A1)
120.00
120.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.500
pers
700.00
350.00
Labour-Un-skilled
1.500
pers
540.00
810.00
Sub-Total(B1)
1160.00
1160.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Manhole Cover
1.000
no.
635.00
635.00
Sub-Total(C1)
635.00
635.00
Total(1)
1915.00
Add over head on Total(1)
3.5 %
67.03
Add Profit on Total(1)
10.0 %
191.50
Total(2)
258.53
Add VAT on Unit Price
5.5 %
15.05
Unit Price
273.57
Say
274
per Nos.