BREAKDOWN OF UNIT PRICE
Item:060102A. Single Layer CC Block over Geotex
Basis:43sft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
4.000
day
60.00
240.00
Concrete Mixer (7/5)
1.000
day
2300.00
2300.00
Excavator
0.500
day
13000.00
6500.00
Sub-Total(A1)
9040.00
2260.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
2.000
pers
700.00
1400.00
Labour-Un-skilled
3.250
pers
540.00
1755.00
Sub-Total(B1)
3155.00
788.75
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
0.450
cum
730.00
328.50
Cement - OPC
0.373
Ton
8800.00
3282.40
Crushed Boulder/Gravel<25
0.420
cum
7250.00
3045.00
Geotextile
2.630
sqm
128.70
338.48
Sub-Total(C1)
6994.38
1748.60
Total(1)
4797.35
Add over head on Total(1)
3.5 %
167.91
Add Profit on Total(1)
10.0 %
479.73
Total(2)
647.64
Add VAT on Unit Price
5.5 %
37.69
Unit Price
685.34
Say
685
per Sqm