BREAKDOWN OF UNIT PRICE
Item:060101. Concrete Slope Protection-100mm
Basis:108sft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
2.000
day
60.00
120.00
Concrete Mixer (7/5)
0.130
day
2300.00
299.00
Sub-Total(A1)
419.00
41.90
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.375
pers
700.00
262.50
Labour-Un-skilled
1.625
pers
540.00
877.50
Sub-Total(B1)
1140.00
114.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
0.450
cum
730.00
328.50
Cement - OPC
0.275
Ton
8800.00
2420.00
Reinforcing Bar Grade 60
0.062
Ton
72000.00
4464.00
Crushed Boulder/Gravel<25
0.775
cum
7250.00
5618.75
G.I. Wire. nails etc
1.000
kg
120.00
120.00
Polythene sheet
10.000
sqm
28.00
280.00
Sub-Total(C1)
13231.25
1323.13
Total(1)
1479.03
Add over head on Total(1)
3.5 %
51.77
Add Profit on Total(1)
10.0 %
147.90
Total(2)
199.67
Add VAT on Unit Price
5.5 %
11.62
Unit Price
211.29
Say
211
per Sqm