Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:051402. CC Block-350x350x200-River Bank
Basis:35cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (2)
6.000
day
60.00
360.00
Concrete Mixer (7/5)
1.000
day
2300.00
2300.00
Excavator
0.250
day
13000.00
3250.00
Sub-Total(A1)
5910.00
5910.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Skilled
1.000
pers
580.00
580.00
Labour-Un-skilled
5.000
pers
540.00
2700.00
Sub-Total(B1)
3280.00
3280.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
0.450
cum
730.00
328.50
Cement - OPC
0.380
Ton
8800.00
3344.00
Crushed Boulder/Gravel<25
0.424
cum
7250.00
3074.00
Geotextile
4.850
sqm
128.70
624.20
Sub-Total(C1)
7370.70
7370.70
Total(1)
16560.70
Add over head on Total(1)
3.5 %
579.62
Add Profit on Total(1)
10.0 %
1656.07
Total(2)
2235.69
Add VAT on Unit Price
5.5 %
130.12
Unit Price
2365.81
Say
2366
per Cum