BREAKDOWN OF UNIT PRICE
Item:051302. Reinforced Earth, Fix Geo-textile
Basis:353cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
2.000
day
60.00
120.00
Vibratory Roller :1-3 Ton
0.150
day
5500.00
825.00
Water Tanker
0.150
day
8000.00
1200.00
Dump Truck
0.150
day
11500.00
1725.00
Pay Loader
0.150
day
14000.00
2100.00
Sub-Total(A1)
5970.00
597.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
1.000
pers
560.00
560.00
Labour-Un-skilled
1.500
pers
540.00
810.00
Sub-Total(B1)
1370.00
137.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
1.000
cum
730.00
730.00
Coarse Sand FM > 2.5
0.747
cum
1836.00
1371.49
Water
10.000
cum
13.00
130.00
Geotextile
11.000
sqm
128.70
1415.70
Sub-Total(C1)
3647.19
364.72
Total(1)
1098.72
Add over head on Total(1)
3.5 %
38.46
Add Profit on Total(1)
10.0 %
109.87
Total(2)
148.33
Add VAT on Unit Price
5.5 %
8.63
Unit Price
156.96
Say
157
per Cum