BREAKDOWN OF UNIT PRICE
Item:050801C. Expansion Joint Complete-D160
Basis:34sft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mobile Genera/Welding m/c
15.000
day
4500.00
67500.00
Lifting Cran-Capacity 25T
8.000
day
46000.00
368000.00
Sub-Total(A1)
435500.00
138714.62
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welder
14.000
pers
700.00
9800.00
Labour-Skilled
8.000
pers
580.00
4640.00
Labour-Semi-skilled
14.000
pers
560.00
7840.00
Sub-Total(B1)
22280.00
7096.58
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Electrode, other Accessor
9.450
LS
1150.00
10867.50
Expansion Joint D160
10.300
m
75000.00
772500.00
Sub-Total(C1)
783367.50
249516.71
Total(1)
395327.92
Add over head on Total(1)
3.5 %
13836.48
Add Profit on Total(1)
10.0 %
39532.79
Total(2)
53369.27
Add VAT on Unit Price
5.5 %
3106.15
Unit Price
56475.42
Say
56475
per m