Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:050801B. Expansion Joint Complete-D120
Basis:34rft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mobile Genera/Welding m/c
15.000
day
4500.00
67500.00
Lifting Cran-Capacity 25T
8.000
day
46000.00
368000.00
Sub-Total(A1)
435500.00
42281.93
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welder
12.000
pers
700.00
8400.00
Labour-Skilled
8.000
pers
580.00
4640.00
Labour-Semi-skilled
10.000
pers
560.00
5600.00
Sub-Total(B1)
18640.00
1809.72
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Electrode, other Accessor
2.053
LS
1150.00
2360.95
Expansion Joint D120
10.300
m
94000.00
968200.00
Sub-Total(C1)
970560.95
94230.05
Total(1)
138321.71
Add over head on Total(1)
3.5 %
4841.26
Add Profit on Total(1)
10.0 %
13832.17
Total(2)
18673.43
Add VAT on Unit Price
5.5 %
1086.81
Unit Price
19760.24
Say
19760
per m