BREAKDOWN OF UNIT PRICE
Item:050102D. Concrete Class-35-RC Girder
Basis:100cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
9.000
day
60.00
540.00
Concrete Poker Vibrator
0.175
day
700.00
122.50
Staging with MS Pipe-Gird
7.000
Sqm
2900.00
20300.00
Mobile Genera/Welding m/c
0.250
day
4500.00
1125.00
Sub-Total(A1)
22087.50
7799.26
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.851
pers
700.00
595.70
Labour-Semi-skilled
1.500
pers
560.00
840.00
Labour-Un-skilled
7.500
pers
540.00
4050.00
Staging of Girder Bridge
7.000
sqm
630.00
4410.00
Fix,Remov Steel Form-Gird
24.500
sqm
170.00
4165.00
Sub-Total(B1)
14060.70
4964.94
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coarse Sand FM > 2.5
1.180
cum
1836.00
2166.48
Cement - OPC
1.290
Ton
8800.00
11352.00
Crushed Boulder/Gravel<25
2.261
cum
7250.00
16392.25
Admixture
2.250
litr
210.00
472.50
Steel Form-PC Girder Brid
24.500
sqm
150.00
3675.00
Sub-Total(C1)
34058.23
12026.22
Total(1)
24790.43
Add over head on Total(1)
3.5 %
867.66
Add Profit on Total(1)
10.0 %
2479.04
Total(2)
3346.71
Add VAT on Unit Price
5.5 %
194.78
Unit Price
3541.49
Say
3541
per Cum