BREAKDOWN OF UNIT PRICE
Item:050101. Single Layer Brick Flat Soling
Basis:1076sft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (2)
10.000
day
60.00
600.00
Sub-Total(A1)
600.00
6.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
3.000
pers
700.00
2100.00
Labour-Un-skilled
7.000
pers
540.00
3780.00
Sub-Total(B1)
5880.00
58.80
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Snd FM > 0.5
9.500
cum
540.00
5130.00
1st Class Brick
3228.000
Nos.
10.00
32280.00
Sub-Total(C1)
37410.00
374.10
Total(1)
438.90
Add over head on Total(1)
3.5 %
15.36
Add Profit on Total(1)
10.0 %
43.89
Total(2)
59.25
Add VAT on Unit Price
5.5 %
3.45
Unit Price
62.70
Say
63
per Sqm