BREAKDOWN OF UNIT PRICE |
Item:031001B. Base Course-DEnsBitumenPG64H-Unmo |
Basis:883cft | |
A1.Equipment |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Vibratory Roller (7-10 T) | 0.250 | day |
11500.00 | |
|
Bitumen Distrubutor | 0.250 | day |
9200.00 | |
|
Tyre Roller PTR | 0.250 | day |
7000.00 | |
|
AC Paver | 0.250 | day |
11500.00 | |
|
Dump Truck | 2.500 | day |
11500.00 | |
|
Asphalt Batching Plant,Gn | 0.250 | day |
128000.00 | |
|
|
Sub-Total(A1) |
70550.00
|
2822.00
|
B1.Labour |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Foreman | 0.250 | pers |
850.00 | |
|
Asplat Mistry | 0.750 | pers |
800.00 | |
|
Labour-Semi-skilled | 1.500 | pers |
560.00 | |
|
Labour-Un-skilled | 1.500 | pers |
540.00 | |
|
|
Sub-Total(B1) |
2462.50
|
98.50
|
C1.Material |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Cement - OPC | 1.200 | Ton |
8800.00 | |
|
Bitumen-60/70 (Bulk) | 3.120 | Ton |
70000.00 | |
|
Crushed Boulder/Gravel<25 | 12.000 | cum |
7250.00 | |
|
Crushed Boulder/Gravel<12 | 4.000 | cum |
6500.00 | |
|
Crushed Boulder < 9 mm | 4.000 | cum |
6400.00 | |
|
Crusher (stone) dust | 17.500 | cum |
1945.35 | |
|
Diesel | 112.500 | ltr |
109.00 | |
|
Angle-62.5x62.5x6-use 20 | 20.000 | m |
200.00 | |
|
|
Sub-Total(C1) |
417866.13
|
16714.65
|
|
|
|
Total(1) |
|
19635.15 |
|
Add over head on Total(1)
|
3.5 % |
687.23 |
|
Add Profit on Total(1) |
10.0 % |
1963.51
|
|
|
|
Total(2) |
|
2650.74 |
|
Add VAT on Unit Price |
5.5 % |
154.28 |
|
|
|
Unit Price |
|
2805.02
|
|
|
|
Say |
2805 |
per Cum |