Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:030302. Aggregate Base Type I
Basis:530cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
3.000
day
60.00
180.00
Vibratory Roller (7-10 T)
0.100
day
11500.00
1150.00
Water Tanker
0.150
day
8000.00
1200.00
Dump Truck
0.150
day
11500.00
1725.00
Pay Loader
0.200
day
14000.00
2800.00
Motor Grader
0.100
day
11500.00
1150.00
Sub-Total(A1)
8205.00
547.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
2.000
pers
700.00
1400.00
Labour-Un-skilled
4.000
pers
540.00
2160.00
Sub-Total(B1)
3560.00
237.33
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
4.875
cum
730.00
3558.75
Crushed Boulder/Gravel<25
3.645
cum
7250.00
26426.25
Crushed Boulder < 9 mm
3.645
cum
6400.00
23328.00
Crushed Boulder < 38 mm
5.835
cum
7400.00
43179.00
Crusher (stone) dust
1.500
cum
1945.35
2918.03
Water
15.000
cum
13.00
195.00
Sub-Total(C1)
99605.03
6640.34
Total(1)
7424.67
Add over head on Total(1)
3.5 %
259.86
Add Profit on Total(1)
10.0 %
742.47
Total(2)
1002.33
Add VAT on Unit Price
5.5 %
58.34
Unit Price
1060.67
Say
1061
per Cum