BREAKDOWN OF UNIT PRICE
Item:030201A. Sub-base - Filter Layer
Basis:530cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
3.000
day
60.00
180.00
Vibratory Roller (7-10 T)
0.150
day
11500.00
1725.00
Water Tanker
0.100
day
8000.00
800.00
Dump Truck
0.150
day
11500.00
1725.00
Pay Loader
0.250
day
14000.00
3500.00
Motor Grader
0.150
day
11500.00
1725.00
Sub-Total(A1)
9655.00
643.67
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
1.000
pers
560.00
560.00
Labour-Un-skilled
3.000
pers
540.00
1620.00
Sub-Total(B1)
2180.00
145.33
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand FM > 1.0
3.000
cum
730.00
2190.00
Brick Khoa < 40mm
15.000
cum
3145.00
47175.00
Water
15.000
cum
13.00
195.00
Sub-Total(C1)
49560.00
3304.00
Total(1)
4093.00
Add over head on Total(1)
3.5 %
143.26
Add Profit on Total(1)
10.0 %
409.30
Total(2)
552.56
Add VAT on Unit Price
5.5 %
32.16
Unit Price
584.71
Say
585
per Cum