BREAKDOWN OF UNIT PRICE
Item:030102. Repair Pothole Existing Pavement
Basis:35cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (2)
6.500
day
60.00
390.00
Bitumen Heater-Tar Boiler
0.500
day
1200.00
600.00
Rishaw Van
0.500
day
700.00
350.00
Sub-Total(A1)
1340.00
1340.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Asplat Mistry
0.500
pers
800.00
400.00
Labour-Semi-skilled
1.000
pers
560.00
560.00
Labour-Un-skilled
4.000
pers
540.00
2160.00
Sub-Total(B1)
3120.00
3120.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coarse Sand FM > 2.5
0.350
cum
1836.00
642.60
Bitumen 80/100 (Drum)
0.100
Ton
66000.00
6600.00
Crushed Boulder/Gravel<25
0.400
cum
7250.00
2900.00
Crushed Boulder/Gravel<12
0.400
cum
6500.00
2600.00
Crusher (stone) dust
0.350
cum
1945.35
680.87
Fire Wood
0.090
Ton
5500.00
495.00
Sub-Total(C1)
13918.47
13918.47
Total(1)
18378.47
Add over head on Total(1)
3.5 %
643.25
Add Profit on Total(1)
10.0 %
1837.85
Total(2)
2481.09
Add VAT on Unit Price
5.5 %
144.40
Unit Price
2625.50
Say
2625
per Cum