Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:030101. Scarify,Mix,Recompact Exist Pavme
Basis:16146sft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
7.000
day
60.00
420.00
Vibratory Roller (7-10 T)
1.000
day
11500.00
11500.00
Water Tanker
1.000
day
8000.00
8000.00
Motor Grader
1.000
day
11500.00
11500.00
Sub-Total(A1)
31420.00
20.95
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
4.000
pers
700.00
2800.00
Labour-Un-skilled
26.000
pers
540.00
14040.00
Sub-Total(B1)
16840.00
11.23
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Water
300.000
cum
13.00
3900.00
Sub-Total(C1)
3900.00
2.60
Total(1)
34.77
Add over head on Total(1)
3.5 %
1.22
Add Profit on Total(1)
10.0 %
3.48
Total(2)
4.69
Add VAT on Unit Price
5.5 %
0.27
Unit Price
4.97
Say
5
per Sqm