BREAKDOWN OF UNIT PRICE
Item:021307. Surcharg Material-Stabliz Sof tGr
Basis:10595cft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (2)
12.000
day
60.00
720.00
Excavator
2.000
day
13000.00
26000.00
Dozer
1.000
day
12650.00
12650.00
Sub-Total(A1)
39370.00
131.23
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Un-skilled
12.000
pers
540.00
6480.00
Sub-Total(B1)
6480.00
21.60
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Soil
30.000
cum
275.00
8250.00
Sub-Total(C1)
8250.00
27.50
Total(1)
180.33
Add over head on Total(1)
3.5 %
6.31
Add Profit on Total(1)
10.0 %
18.03
Total(2)
24.35
Add VAT on Unit Price
5.5 %
1.42
Unit Price
25.76
Say
26
per Cum