BREAKDOWN OF UNIT PRICE
Item:021305. Sup, Inst, Monitor Settlment Plat
Basis:4no.
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
10.000
day
60.00
600.00
Excavator
1.000
day
13000.00
13000.00
Sub-Total(A1)
13600.00
3400.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
5.000
pers
560.00
2800.00
Labour-Un-skilled
10.000
pers
540.00
5400.00
Sub-Total(B1)
8200.00
2050.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Plate-6/10 mm thick
96.110
kg
92.00
8842.12
Sub-Total(C1)
8842.12
2210.53
Total(1)
7660.53
Add over head on Total(1)
3.5 %
268.12
Add Profit on Total(1)
10.0 %
766.05
Total(2)
1034.17
Add VAT on Unit Price
5.5 %
60.19
Unit Price
1094.36
Say
1094
per no.