BREAKDOWN OF UNIT PRICE
Item:021304. Construction of Vertical Drain
Basis:66rft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
6.000
day
60.00
360.00
Vibratory Roller (7-10 T)
0.250
day
11500.00
2875.00
Excavator
0.250
day
13000.00
3250.00
Sub-Total(A1)
6485.00
324.25
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Semi-skilled
3.000
pers
560.00
1680.00
Labour-Un-skilled
5.000
pers
540.00
2700.00
Sub-Total(B1)
4380.00
219.00
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coarse Sand FM > 2.5
1.400
cum
1836.00
2570.40
Sub-Total(C1)
2570.40
128.52
Total(1)
671.77
Add over head on Total(1)
3.5 %
23.51
Add Profit on Total(1)
10.0 %
67.18
Total(2)
90.69
Add VAT on Unit Price
5.5 %
5.28
Unit Price
95.97
Say
96
per m