BREAKDOWN OF UNIT PRICE
Item:021303. Supply, Laying Geo-textile Fabric
Basis:108sft
A1.Equipment
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Small hand tools (1)
0.500
day
60.00
30.00
Sub-Total(A1)
30.00
3.00
B1.Labour
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Un-skilled
0.200
pers
540.00
108.00
Sub-Total(B1)
108.00
10.80
C1.Material
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Geotextile
10.500
sqm
128.70
1351.35
Sub-Total(C1)
1351.35
135.14
Total(1)
148.94
Add over head on Total(1)
3.5 %
5.21
Add Profit on Total(1)
10.0 %
14.89
Total(2)
20.11
Add VAT on Unit Price
5.5 %
1.17
Unit Price
21.28
Say
21
per Sqm